PROVISIONAL SUMS

 

 

 

Just lately, I have noticed a growing tendency on the part of the Design team to use the existence of Provisional Sums in the original Bills as an excuse for rejection of the Subbie's claims for delay and loss and expense.  The party line is based on a fond belief that such an inclusion, however vague, gives the Design team a licence to introduce as much additional work as they wish, and as late as they choose, on the basis that the Subbie "should have made due allowance in his tender".  What super fun, chaps.  Unfortunately, it's a load of baloney.  So let us look at the true position.

 

 

Where a Bill has been prepared in accordance with SMM7, the rules are very clear, and make good news for Subbies.  Provisional Sums are to be  classified in the bill as either "Defined" or "Undefined".  If "Defined", then the Subbie is deemed to have made due allowance in his programming, planning and pricing of Preliminaries. However, the good news is that in order to qualify for the title of "Defined", the Bill item shall give information about (a) the nature and construction of the work (b) how and where the work is fixed to the building and hat other work is fixed thereto (c) a quantity or quantities which indicate the scope and extent of the work (d) any specific Employer's  limitations and requirements. If all this information is not given, then the Provisional Sum does not qualify for the title of "Defined", even if so described in the Bill.  Furthermore, even when properly "Defined" in the Bill, the Subbie is still entitled to delay costs and extension of time, if appropriate, in the event that the Design team is late with the issue of instructions for which the Subbie applied in writing in reasonable time.

 

                                      

As to "Undefined" Provisional Sums, the Standard Method states that the Subbie will be deemed not to have made any tender allowance in programming, planning and pricing Preliminaries. Therefore, as and when such sums are instructed, the work involved is, in effect, a variation for "additional work", and the Subbie is therefore entitled to his full entitlements as regards additional preliminaries (ie engineering and supervision involvement etc) and appropriate extension of time and loss and expense where this is merited by the nature, timing and volume of the work involved.  All this is spelled out in Amendment 7 to DOM/1 (September 1989). Not bad, eh?

 

 

All this small print appears to have been lost on the Architect who recently rejected my Subbie friend's claim for delay, even though the sums were "Undefined" and he was happily issuing information weeks after the end of the original sub-contract period.  Don't worry, we shall make sure that justice is done in due course!

 

 

So the moral is not to take everything the Architect and/or PQS say to you as gospel, just because you're a humble Subbie.  The streetwise Subbie should check things out for himself and then act accordingly.  So cheer up, chaps!

 

 

 

Keynote:        

 

Don't be conned by "Undefined" Provisional Sums.

 

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

 

Back to Jack Russell Column Contents

 

Back to home page