WHAT MAKES A GOOD NOTICE?

 

 

It is quite amazing just how "bad" an apparently "good" letter or notice can actually be. What seems like a clear and meaningful communication at the time when the daily events are in the forefront of everyone's minds can in fact prove almost useless when trying to prove your case for delay at the end of an over-run job.  A typical  example:

 

"We confirm our site  discussions of yesterday, when we notified you that we are unable to commence our installations on level 2, due to lack of readiness by other trades. This may well affect our programme, and will certainly cause disruption for which we reserve the right to seek costs if necessary".

 

Looks pretty good, eh?  Certainly. But imagine having to rely on this notice a year later, as one of the reasons why you finished late.  The questions which then arise would be:

 

Discussions with whom?  What other trades exactly?  What is 'not ready'?  Which programme activity is affected?  What is the actual effect?  What is the disruption?  "Reserve rights" is a useless term - is the Subbie registering a claim or not?

 

In fact, it is not necessary to be a "man of letters" or even a "contractual smart arse" in order to write a good letter.   Some of the things to bear in mind are:

 

·       Each letter should be "self contained" and therefore "make sense" to some stranger in two years time, without a lot of expensive detective work".

 

·       Each letter should confine itself to the simple facts, without any expressions         of emotion, or references to irrelevant side issues.

 

·       It is a good idea to put the "subject heading" at the top of every letter, thereby saving       hours of "ransacking files" both during the job and thereafter.

 

·       Each letter should be given a unique reference number - a simple device which can save time and frustration for all parties involved.

 

·       The letter should be written at the time when the problem in question is "hot".

 

As regards contractual "notices" of delay and/or disturbance, it is optimistic to expect that the Site Engineer and/or Supervisor will always have at his elbow the full set of sub-contract and main contract conditions detailing clause numbers and notice requirements, time limitations etc.  Therefore, it is more important to "Bang it in, Bill" than it is to create some superb legalistic document. 

 

In fact, the requirements of most Conditions are very similar. It boils down to this - the guy with the purse strings is entitled to know immediately there is a "problem", because nobody likes "nasty surprises" after the budget is spent.  Furthermore, he is entitled to be told the exact nature of the problem, how it came about, the immediate effect on programme and progress,  the likely effect on overall completion and any cost implications.  Several text books express it on these lines:

 

§       Notice in writing forthwith for each individual delaying or disrupting event as soon as it becomes apparent.

 

§       Emphasise that the memo or letter is a "notice".

 

§       Give material circumstances including causes of delay or disturbance.

 

§       Identify "Relevant event" in conditions.

 

§       Give expected effect on programme/progress (ie specify the affected activity and how so).

 

§       Give estimate of length of delay to completion of overall sub-contract works.

 

§       Give details of any cost effects.

 

·       Update as necessary.

 

 

If you can do this, without being "bolshy" or emotive, the Client and/or Builder will have a chance of doing something about it at the time.  That is in everybody's interests. 

 

Keynote:

Make sure each  letter and notice will stand on its own merits 

to protect you  now and in the future.

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

Back to Jack Russell Column Contents

Back to home page