PROTECTING THE SUBCONTRACTOR’S ENTITLEMENTS

 

Many subcontractors start off every job on the proposition that this time it will all go swimmingly, when in fact experience shows otherwise. The “streetwise” subcontractor should set up    at the outset, and maintain certain basic strategies which will protect his entitlements to time and money. 

 

So what are these strategies? Well, they do not involve rocket science but are based primarily upon good “contractual housekeeping”. These basic routines include the following:

 

 

Confirm Start and Completion Dates (both overall and for individual sections).

The actual commencement date is fundamental to “starting the clock” (ie setting the subcontract period running). As to the date of practical completion, this determines the cessation of any liability to damages for delay and triggers off the commencement of the defects period and release of half retention.  The subcontractor should make sure that these important dates are recorded in writing at the time. 

 

Record and confirm all Programme Agreements and Revisions.

Programmes are often passed to and fro in an all too casual manner. The streetwise subcontractor should make sure he has an agreed and identified programme at the outset, and that  every revision is dated and covered by an appropriate instruction from the contractor. Is the revised programme merely “for discussion”? Or does it constitute a definite instruction from the contractor?  These questions should be resolved at the time of issue.  Examine each revised programme and compare with the original issue, particularly as regards the structure itself. If the roof and the windows have slipped three months and the electrical works are still shown finishing on the original date, then there is something very wrong. If spotted at the time of issue, and dealt with at that time, subsequent disputes regarding time are greatly reduced.

 

Notify all delays to client/contractor  immediately they become apparent.

Many subcontractors shrink from giving notice of delay for fear of “upsetting the client”. In fact, it is in every party’s best interests if all potential delays are flagged up at the time. In many cases, this enables agreed actions to be taken to remove or minimise the delay.  In any event, if the subcontractor is going to be delayed, he may well need to prove his entitlements to extension of time, and without such written notices he will be unable to do so. After all, virtually all subcontract conditions insist that the subcontractor does promptly serve such a notice.

 

Notify client/contractor of effect of delays to overall completion date.

Again, all subcontract conditions dictate that the subcontractor should serve written notice as soon as he becomes aware of any possible delay to completion. If the project is to be delayed in completion, then the sooner someone tells the client the better. Nobody will love the subcontractor for this news, but they will love him a lot less if it comes as a last minute surprise.  If the subcontractor is to preserve his entitlements to extension of time, then it is absolutely essential that he notifies any such threat to the completion date, and states the reasons.

 

Apply for extension of time when  necessary.

Many forms of subcontract do not actually require the subcontractor to request an extension of time, but only to notify the delays to his progress and/or completion. However, the prudent subcontractor will, as soon as he sees his works running beyond the original completion date, make sure he submits a written request for extension, stating the detailed reasons. Remember, if the subcontract works run over the end date, then only an extension of time award will protect from damages.

 

Confirm all instructions in writing.

Most subcontract forms state that no variation is to be carried out without a prior written instruction from the client/contractor.  The subcontractor should try to follow this requirement at all times. At the very least, any informal or oral instruction must be confirmed in writing forthwith, and followed up later.  Remember, all work carried out without a formal instruction is potentially at risk in terms of payment. Also, make sure  the person issuing the instruction has the contractual authority to do so.

 

Submit dayworks records for signature at the time

Dayworks should be submitted for signature daily or at the latest,  the end of the working week. If the subcontractor delays in doing so, he can hardly complain if the recipient is unwilling to sign.

 

Keep  good site records, photographs etc

There is no substitute for first class  records such as the site diary, labour allocations, requests for information, progress reports, drawings registers etc. As to site photographs, these can be invaluable, but only if dated and referenced as to location and significance. 

 

 

Recognise “variation” and  “claims type” situations (eg  additional costs due to changes, “extras”, delays, return visits, “piecemeal working” etc) as they become apparent and notify the client/contractor forthwith.

All too many subcontractors wait until the end of the job before pricing and submitting their variations, claims for prolongation and the like. Not only is this a failure under the subcontract  terms, but it also comes as a nasty surprise to the recipient. If there is nothing in the project budget, the glossiest submission will be of no use.

 

Promptly apply for payment,  with  detailed evaluations.

Most subcontract forms now insist that only a “valid” application will be considered. The term “valid” is usually defined as meaning that all inclusions must be fully detailed and supported by all necessary instructions, copy invoices, signed dayworks etc.  So a subcontractor who submits vague “on account” applications with no proper validation will find his application dismissed without payment.

 

Conclusion

In a nutshell, my advice to the subcontractor is :

Put it in  writing at the time! 

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

Based on my column in Electrical Times,  April 2006 edition – Contract Law.

 

Back to Jack Russell column for more articles like this one.

 

To John Russell Home page and site layout.