PROGRAMME PROBLEMS

 

 

A reasonably detailed programme is an absolute “must” for any sizeable sub-contract.  How else can a sub-contractor plan his resources, monitor his progress and identify potential and actual delays?  Many sub-contract agreements and orders contain only vague information regarding the vital matter of programme.  In such a scenario, the sub-contractor  risks becoming a “contractual prisoner”. Indeed, that is precisely how many main contractors like to run the project.  So let us consider some basic steps to avoid those “programme problems”.

 

Firstly, under no circumstances enter into a sub-contract arrangement merely on the basis of a loose form of words. Typical examples of such clauses include “in accordance with main contractor’s directions”, “to suit the progress of the main contractor”,  “in accordance with main contract programme” etc.  This type of clause places an open ended obligation upon the sub-contractor.

 

As an absolute minimum, the original order or agreement should contain a “starting window”  for commencement, a period for giving of written notice to commence and a  number of weeks for carrying out the works on site.  Always clarify whether these are “working weeks” or “calendar weeks”.

 

If possible, try to agree a detailed sub-contract programme and have it incorporated by specific reference into the original order or agreement.  If that proves impossible, then endeavour to agree a sub-contract programme before you commence the works, and make it clear that this will be your "baseline" for planning and reporting purposes.  The longer you take in reaching agreement on a detailed sub-contract programme, the more likely it is that your agreed programme will take on board  delays and problems that did not exist at tender stage.

 

Try to obtain a copy of the main contractor’s overall project programme. This will help you to understand more clearly where your works interface with those of other trades and therefore to foresee and notify possible problems in a proactive manner. It will also help you to monitor the overall project progress and identify the implications upon your own works.  If the project falls into significant delay, this information will assist you in demonstrating the true causes (ie delay in access to work faces etc) and to obtain an extension of time under the sub-contract.

 

If the main contractor declines to provide you with a copy of his overall programme,  then produce and submit  a list of vital “dependencies” for such pre-conditions as “building watertight”, “statutory  power available” etc. At least, you will be building in some degree of protection as and when these dependencies fall behind.

 

Confirm all programmes in writing, both those you issue and those received from the main contractor. Make sure each programme is date stamped.  Before you commence working to any new or revised programme, establish the actual status. Is it intended that you now work to this programme? If so, you need a written instruction before you comply. Perhaps it is intended merely “for discussion”. Again, clarify the precise position in writing. 

 

When issued with a new or revised programme, many sub-contractors merely scroll down until they get to the activities relating to their own works.  In fact, a prudent sub-contractor should examine the overall programme and what it indicates regarding the project as a whole.  If the roof and windows have slipped back several months and yet  the overall completion date is still the same, then further examination will no doubt show that the revised programme has been “compressed”, and the various trades, together with the sub-contractor’s own activities, will now show “stacked” working, culminating in a “grandstand finish”. Very often, in such programmes, the original period of residual commissioning activity will have disappeared completely.    Such programmes – and they are very common – almost always fail.  The time to address the problem is now, before you expend excessive resources and finances in attempting to work to a revised programme that is doomed from the start.

 

If the main contractor issues a revised programme which shows the overall completion date slipping back by  several weeks or months, it is wrong to assume that this automatically bestows an extension of time upon the sub-contractor.  In such a case, it is up to the sub-contractor to interrogate the programme and to identify the reasons for the movement in his own activities, and then to apply for a formal extension of time, specifying the relevant events.

 

 

 

Whilst it is normal to monitor and report actual progress by reference to the current revision of the programme, remember that a sub-contractor’s "contractual performance" (i.e. in relation to extension of time, damages etc) is measured against the original programme, until such time as a formal extension of time is granted. 

 

All too many sub-contractors allow themselves to be dragged along without any clear indication as to the main contractor’s intentions. This is the road to financial disaster. The streetwise sub-contractor will do his best to ensure that at all times he has a meaningful, up to date programme against which to plan and manage his works.

 

 

This article is based on the “Contract Law” column in Electrical Times June 06.

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

Back to John Russell Home page

 

Back to the Jack Russell column.