GETTING
PAID IN THE CONTRACTS JUNGLE
For most sub-contractors, “getting paid” is a constant problem.
Clients and main contractors will use every trick n the book, it seems, to
reduce and delay payments. All too
often, the sub-contractor’s efforts to remedy this situation are implemented
too late in the process (eg only when his accounts show that the payment is overdue
and/or significantly reduced).
In fact, to be successful, the
process of “getting paid in full and on time” should start at the outset – at
enquiry stage, and be followed in a systematic manner throughout the progress
of the works and the eventual final account.
Some basic steps are set out below:
The enquiry and tender – identify and
address the risks
Remember the “five W’s” :
· Who is the enquiry from?
· What is the work scope?
· Where is the work located?
· When will it be carried out?
· What is the credit rating of client and main contractor?
If the enquiry fails the above test, this is the time to politely
decline. “Turn-over for turn-over’s
sake” is of no benefit whatever. If the sub-contractor decides to proceed with
the tender,
·
Vet the proposed
terms and conditions.
·
Check payment terms
and periods.
·
Beware set off and
other onerous clauses.
·
Price the risk,
or attempt to negotiate better terms.
Payment terms to beware of include :
·
Extended payment
periods.
·
Pay when certified
under the main contract.
·
Unclear payment
procedures.
·
Conditions precedent
(ie no payment unless certain pre-conditions fully complied with by the
sub-contractor).
·
No payment until all
sub-contract documents, warranties, bonds etc executed and returned.
·
“Pay if paid” in
event of the end client’s
insolvency.
·
Excessive retention
percentages.
·
Retention release
geared to the main contract defects certificate.
Letters of intent
·
Agreed sub-contract
tender sum and work scope.
·
Programme period and
start date.
·
Reference to the
terms and conditions.
·
Definite instruction
to start defined work on a specific date..
·
Promise to pay up to
a stated sum if a formal sub-contract agreement is not achieved.
The order
It is understandable when a
sub-contractor reacts gleefully to the receipt of an order for which he has worked
so hard. However, when the celebration is over, it is vital to check the order
in detail against the submitted tender.
·
Check the value, including any discount and
retentions.
·
Check the programme
dates and period.
·
Check the sub-contract terms and conditions.
·
Check the payment
terms, dates and durations.
·
Check for “counter
offers” (ie new and onerous terms introduced into the order).
·
Beware acceptance by
conduct (ie signifying acceptance by starting work).
Getting paid on site.
·
Find out who is
responsible for dealing with the sub-contractor’s interim application (usually
the main contractor’s quantity surveyor).
·
Make contact with
the appointed person and discuss the process in more detail.
·
Ascertain the level
of detail and substantiation required for the application.
·
Find out the dates
by which applications must be submitted.
·
Ensure the
applications are submitted by the required dates.
·
Provide full details
and include sums in respect of any “claims”, variations, additional costs etc.
·
“Get it in the
budget” if you can. Nobody likes nasty
surprises at the end of the job.
Monitoring and pursuing payments
The sad fact of life is that main contractors tend to push “nice
guys” to the back of the queue. So the sub-contractor must set up a systematic
procedure for monitoring and pursuing payment.
This requires a lot more work than the traditional approach of waiting
until the payment fails to arrive before taking belated action.
·
Establish and
monitor the dates by which the main contractor’s notification should be
received.
·
Chase immediately if
an expected notification fails to arrive on the appropriate date.
·
Establish and
monitor final dates for payment (ie dates by which the cheque is
expected).
·
Chase immediately if
an expected payment fails to arrive on the appropriate date.
·
Consider giving notice
of suspension if payment of the notified sum is overdue. (Be careful to check
the number of days notice required under the sub-contract conditions).
·
Demand reasons for
under-payment. Consider threatening adjudication in cases of persistent or
unacceptable late or reduced payment.
Protecting cash flow when on site
The sub-contractor needs to be commercially aware at all
times. This awareness includes :
· Keeping good site records.
· Establishing authority on day one (ie who is authorised to give the
sub-contractor instructions and to sign dayworks sheets etc).
· Obtaining written instructions before embarking on variations.
· Ensuring dayworks sheets are submitted promptly for signature.
· Promptly notifying all delays and additional costs.
· Applying for extension of time if the completion date is threatened
by a relevant event.
· Applying for “claims” (ie delay and disruption costs) as soon as
the situation becomes apparent.
Conclusion
It can be seen from the above that the process of obtaining full
and timely payment is far more than just a “credit control” function. On the
contrary, the process must be implemented at enquiry stage and maintained
throughout as part of a disciplined set of procedures. In short, cash flow is everybody’s
responsibility, not just the credit control clerk!
Based on my “Contract Law” column in “Electrical
Times” published 1 August 06.
John Russell
Contracts and
Training Consultant
Cheshire CW4 7DP
Tel: 07770 986444
Email: swsubbie@globalnet.co.uk
Home
Back to Jack
Russell column