DELAYS TO PROGRAMME

 

 

 

Dear Uncle Jack

I am a contracts engineer. The job is falling badly behind programme, due to building delays, late information and variations. It is obvious that I am going to over-run the end date by several weeks. What should I do? What are my entitlements?

 

 

Dear Worried Engineer

The first action is to protect yourself from the risk of damages. If the project handover is delayed and the builder considers you to blame, he will set off from your account the costs of his site staff and establishment, plus the liquidated damages he is likely to suffer from the client. So a few weeks over-run can amount to a financial disaster.

 

Your protection must come from submitting prompt delay notices as individual delays become apparent, recording the exact circumstances, the date and area, the programme activity affected and the estimated effect upon the completion date.  As and when you see the overall completion date being endangered, you must notify in writing, requesting an extension of time, stating your reasons. You must then update these requests as and when necessary.  Be ready to chase the builder. Don’t be fooled by vague promises. As and when you get a written extension of time, then you are protected from damages.

 

If the reasons for delay are due to the builder or client, you are usually entitled to claim prolongation costs. Such reasons include late variations, additional workload, late information, delays by the end client or his direct contractors, delays by the builder or his sub-contractors.   These costs are called “loss and expense”.  It is essential that you notify your claims promptly in writing.  Give the builder budget figures, then update as necessary. If you fail to do this, you lose all entitlements.

 

Prolongation costs include site engineers, supervisors, charge hands, welfare man, storekeeper, site offices, cabins, telephone, fax, plant and tools.  Also claimable is the time of visiting head office people like contracts managers, surveyors, planners.  As regards  head office overheads generally, the simplest way is to add a percentage to the total claim.  Even better is to make certain all head office people book their time to individual contracts, and then “job cost” their time on a weekly basis. This makes it easier to recover your  entitlements.

 

Having submitted your claims, be a nuisance. Nice guys get ignored.

 

 

 

 

Home.htm

 

 

 

John Russell  

 Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk