THE NEW “DELAY AND DISRUPTION PROTOCOL”

A COMMENTARY – Part 6

 

 

In order to follow the Society of Construction Law’s  “Delay and Disruption Protocol” we must be aware of its terminology.  The SCL’s document includes a  comprehensive glossary, and we list below some of  the principal definitions.

 

compensation

The recovery or payment of money for work done or time taken up whether by way of valuation, loss and/or expense or damages.

 

compensable event

Expression sometimes used to describe what in the protocol is an Employer Risk Event in respect of which the contractor is entitled to compensation.

 

concurrent delay

True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time.

 

contractor delay

Expression commonly used to describe any delay caused by a Contractor Risk Event. The protocol distinguishes between: Contractor Delay to Progress which is a delay which will merely cause delay to the contractor’s progress without causing a contract completion date not to be met; and Contractor Delay to Completion which is a delay which will cause a contract completion date not to be met.

 

contractor risk event

An event or cause of delay which under the contract is at the risk and responsibility of the Contractor.

 

 

critical path

The sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration. There may be more than one critical path depending on workflow logic. A delay to progress of any activity on the critical path will, without acceleration or re-sequencing, cause the overall project duration to be extended, and is therefore referred to as a ‘critical delay’. 

 

culpable delay

Expression sometimes used to describe what the protocol calls Contractor Delay.

 

delay event

An event or cause of delay, which may be either an Employer Risk Event or a Contractor Risk Event.

 

disruption

Disturbance, hindrance or interruption of a contractor’s normal work progress, resulting in lower efficiency or lower productivity than would otherwise be achieved. Disruption does not necessarily result in a Delay to Progress or Delay to Completion.

 

employer delay

Expression commonly used to describe any delay caused by an Employer Risk Event. The Protocol distinguishes between Employer Delay to Progress which is a delay which will merely cause delay to the contractor’s progress without causing a contract completion date not to be met, and Employer Delay to Completion which is a delay which will cause a contract completion date not to be met.

 

employer risk event

An event or cause of delay which under the contract is at the risk and responsibility of the Employer.

 

float

The time available for an activity in addition to its planned duration. See free float and total float. Where the word ‘float’ appears in the Protocol, it means positive not negative float, unless expressly stated otherwise.

 

 

free float

The amount of time that an activity can be delayed beyond its early start/early finish dates without delaying the early start or early finish of any immediately following activity.

 

head office overheads

Head office overheads are the incidental costs of running the Contractor’s business as a whole and include indirect costs which cannot be directly allocated to production, as opposed to direct costs which are the costs of production. Amongst other things, these overheads may include such things as rent, rates, directors’ salaries, pension find contributions and auditors’ fees. In accountancy terms, head office overheads are generally referred to as administrative expenses, whereas the direct costs of production are referred to as costs of sales.

 

liquidated and ascertained damages, liquidated damages, LADs, LDs

A fixed sum, usually per week or per day, written into the contract as being payable by the Contractor in the event that the works are not completed by the contract completion date (original or extended).

 

mitigation

Mitigate means making less severe or less serious. In connection with Delay to Progress or Delay to Completion, it means minimising the impact of the Risk Event. In relation to disruption or inefficient working, it means minimising the disruption or inefficiency. Failure to mitigate is commonly pleaded as a defence or partial defence to a claim.

 

prolongation

Prolongation is the extended duration of the works during which costs are incurred as a result of a delay.

 

Amendments are currently being prepared in order to allow for the introduction of key elements of the protocol into the industry’s standard forms. In the next article, we shall consider how and to what extent this is likely to affect us.

 

( Contract Law column for Electrical Times published 1 March 2004)

 

Home

 

Back to Jack Russell page

 

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

                         Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk