THE NEW “DELAY AND DISRUPTION PROTOCOL”

A COMMENTARY – Part 5

 

 

“Change management supplements” are about to be published to enable the incorporation of  the Society of Construction Law’s  “Delay and Disruption Protocol” into JCT standard forms.   It is vital that services contractors are aware of the protocol’s key features. Our commentary on the protocol this month focuses on the programme  and management of changes. The writer’s comments are  given in italics.

 

Accepted programme

The protocol recommends that the contractor should submit his programme as early as possible, for acceptance by the main contractor or client, to be used as the prime tool for managing change and delays 

 

Format should be agreed in advance and reflect the size and complexity of the works. Except for very simple contracts, planning software should be agreed for mutual use.  The programme should be in electronic form, capable of interrogation by both parties.  It should identify critical path, relevant activities including design and procurement, information requirements, approval dates and linkage to the various activities. The programme should be cross-referenced to a method statement detailing the contractor’s intentions and resources.  (In fact, all sub-contractors should include on their programmes details and dates of dependencies required of the main contractor. These include key access dates, works by other trades, watertight dates, availability of mains power etc. These are usually the prime sources of delay in any project. The sub-contractor is then able to monitor and report on these dependencies, thereby protecting himself and notifying the main contractor of key actions to expedite progress).

 

Acceptance does not make the programme a formal contract document, although this can be so if the parties choose.  Every effort should be made to achieve an accepted programme as early as possible. The protocol suggests financial incentives or even withholding of a set sum until a proper programme is submitted

 

The accepted programme is to be regularly updated, not less often than monthly, using the agreed software. On large projects this updating may have to be more frequent.  The contractor must enter actual dates and percentage progress achieved on the various activities. These updated programmes are to be retained in hard copy as a permanent record. It is the latest updated programme which is then used to monitor subsequent progress.  Where the contractor has incurred his own delays, he can be made to issue a further programme showing how he intends to reduce same.

 

The protocol gives guidance on the detailed planning approach. The recommended format is a linked bar chart (cascade diagram).  Labour and plant resources, major materials and work rates should be indicated for each activity.

 

Extension of time

This is to be based upon the accepted and updated programmes. A “sub-network” is to be inserted into the updated programme to show the actual or anticipated impact of a client or main contractor event.   In the absence of a compliant submission, then the client or main contractor should make his own evaluation.  Any disagreement should be resolved as quickly as possible, if necessary by using the prescribed dispute procedure.   Such disputes are not to be left until the end of the project.

 

The programme is to be brought fully up to date prior to entering the sub-network representing the client or main contractor event. The impact can then be determined by use of the agreed planning software. The methodology used is described as “time impact analysis”.  Where there is concurrent delay (ie separate but parallel delays attributable to both parties), any culpable delay by the contractor should not reduce the entitlement to extension.

 

Records

Whilst the programme is the primary tool for determining extension of time, reference will also be necessary to contemporary records.  The protocol recommends that the range and format of records should be agreed at the outset.  (This is an excellent proposal.  Be aware that the various programmes and progress reports are unlikely to satisfy the notice requirements of most contract conditions. There will be an even greater need for timely and compliant delay notices).

 

Conclusion

(The recommended procedures appears  too expensive and time consuming for use on smaller and midsize projects. There will be a need for technical staff to ensure compliance. In particular, there will be a need for more planners.  Only a few major sub-contractors will have the necessary resources. The big worry is that many ordinary sub-contractors may forfeit their entitlements to time and money as a result. Any sub-contractor who drifts unaware into a project governed by this protocol may well risk disaster. Get prepared now).

 

 

 

 

 

 

 

 

 

Home page

 

 

 

Back to Jack Russell column

 

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk