4 April 2005

 

 

GOVERNMENT REVIEW OF CONSTRUCTION ACT

 

Clamp down on  tricks and dodges?

 

 

 

The DTI has brought out a consultation paper (running to nearly 120 pages) entitled “Improving payment practices in the construction industry”.  This document, which also deals with adjudication, sets out in copious detail the numerous matters which have been considered and the resultant proposals for consultation.

 

The proposals are stated to be aimed at improving the ability of parties to a construction contract to:

 

 

·     Reach agreement on what should be paid and when given the work done under the contract or, where they cannot agree, to make an informed referral to, or response at, adjudication.

 

·     Manage cash flow and enable completion of work on the project in the event of problems such as defaulted payments, disputes or insolvencies elsewhere in the supply chain; and,

 

·     Refer disputes to adjudication without disincentives such as avoidance, frustration or unnecessary challenge.

 

The full document can be obtained by contacting the DTI’s construction web site.  The main proposals are briefly summarised below, with the more important reforms highlighted in bold italics.

 

 

 

Key proposals regarding payment

 

 

1.  Defining the content of an adequate payment mechanism in Section 110(1) of the Construction Act.

 

2.  Removing the requirement to serve a Section 110(2) notice in the Construction Act

 

3.  Providing an application for payment in the legislation.

 

4.  Redefining the content of withholding notices under Section 111.

 

5.  Restricting the use of pay-when-certified clauses.

 

6.  Introducing a right to reimbursement for the costs of suspension and remobilisation and providing additional time for remobilisation under Section 112 of the Construction Act.

 

7.  Making contractual provisions on cross contract set-off ineffective.

 

8.  Making "pay-when-paid" clauses ineffective in cases of "upstream" insolvency proceedings.

 

9.  Allowing stage payments under the Scheme for Construction Contracts to be made for materials in advance of their arrival on site

 

 

 

 

Key proposals regarding Adjudication

 

 

10.  Preventing the use of "trustee stakeholder accounts" to suspend an adjudicator's award pending litigation other than when the recipient is involved in insolvency proceedings

 

11.  Providing the adjudicator with the power to rule on certain aspects of his own jurisdiction and providing a right to payment in cases where the adjudicator stands down due to lack of jurisdiction

 

12.  Providing the adjudicator with the right to overturn "final and conclusive" decisions where these are of substance to interim payments only.

 

13.  Extending the adjudicator's immunity under the Construction Act to claims by third parties.

 

14.  Applying provisions on adjudicator independence from the Scheme for Construction Contracts' to all adjudications in Section 108 of the Act

 

 

 

Improving adjudication in the construction industry

 

Legislation is also planned for the parties to an adjudication to  bear their own legal and other costs while the costs of the process (the adjudicators fees and expenses and the costs of his appointment) are referred to the adjudicator to be decided as part of his decision of the dispute. 

 

However, once a dispute has been referred to an adjudicator, if both parties also wish to refer the legal costs they incur in the process, the adjudicator should also award these as part of his decision of the dispute.

 

 

 

Proposals submitted by Sir Michael Latham but not to form part of the DTI consultation.

 

The DTI consultation paper lists various matters which, whilst emerging from Sir Michael’s review, will not be part of the  consultation. Amongst  the reasons is where the position is already covered by case law or other legislation.  The three principal areas of non-consultation are :

 

1.  Issues previously consulted on in "Improving Adjudication in the Construction industry”.

 

2.  Proposals to legislate only to provide clarification of the existing law as established by the courts

 

3.  Proposals to legislate to introduce measures for construction contracts affecting the framework of other late payment or insolvency legislation relating to all industry sectors.

 

Also, the DTI will not be  consulting on:

 

·     Amending the meaning ‘of evidenced in writing’.

·     Amending the scope of the existing legislation.

 

 

 

Jack Russell’s comments

 

 

Some tricks and dodges dealt with in the proposals include : 

 

 

·     “Pay when certified”.

·     “Pay when paid”,

·     Cross set-off between different sub-contracts.

·     Stakeholder accounts, which delay payment of adjudication awards,

·     “Final and conclusive” clauses, which prevent action by the adjudicator.

·     “Referring party pays all costs and fees” of adjudication, regardless of outcome.

 

 

 

Sub-contractors may not have got everything from this review that they would wish.  However, if these proposals are implemented, many clients and main contractors will  find it a lot more difficult to use their bespoke terms as an instrument for “subbie bashing”!

 

 

 

(This article is based on the “Jack Russell” contract law column in the “Electrical Times”).

 

 

 

 

Back to Jack Russell column for more articles on contract law.

 

 

 

To John Russell home page for tour of web site.

 

 

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk

 
s