DON’T STICK YOUR NEC OUT

 

 

 

 

The New Engineering Contract (NEC)  is being used ever more widely in our industry, notably by health, education, water treatment and local authorities. Sooner or later, it is inevitable that most major and medium sized electrical subcontractors will find themselves invited to tender on the NEC forms. 

 

 

If a subcontractor is suitably prepared and his staff have received appropriate training,  the NEC has many advantages over the traditional contract forms. However, if he wanders unaware into an NEC project assuming that this is another contract which can be signed  and put away in the safe, then he will be in for a very painful experience. Indeed, I have known reputable subcontractors to lose vast sums precisely for this reason.  So what are the key aspects of which to be aware?

 

 

The NEC is based on a philosophy of “mutual trust and co-operation”.  I would caution against excessive reliance upon trust. Indeed, the NEC rules are so detailed and precise that there is little scope for trust. Quite simply, the subcontractor must comply with the rules to the letter. If he does not, he will suffer financial consequences.  There are three “big ideas”, as follows.

 

 

1)     Programme

 

·    To  be provided and updated as works proceed.  Highly detailed.

·    25% deduction from payment as financial penalty for failure to provide.

 

 

 

2)     Compensation events

 

·    The only mechanism for additional payments, “claims”, “changes” (variations)etc.

·    Basis is actual cost and/or forecast of actual cost, plus a fee percentage (as contract data).

·    No provisions for “top ups” or residual “end of job claims”.

·    Written notice required within one week or entitlements are lost.

·    Quotation and forecast of programme effect  required within one week if event accepted.

·    Idea is to “value changes, delays and disruptions as the job proceeds”.

 

 

 

3)     Early warning procedure

 

·    The subcontractor and contractor each  have a duty to give early warning as soon as aware of any matter which could increase prices, delay completion or impair performance of the works.

 

·    Either party may instruct the other to attend an early warning meeting, along with relevant other parties.

 

·    If this procedure results in a compensation event, then a separate notice must be given.

·    If the subcontractor fails to give an early warning notice when he should , then any compensation event is priced as though  he had done so (ie in which case the contractor would have been able to take action to avoid or reduce the problem).

 

 

It is absolutely essential that the subcontractor complies with all the rules and time limits to the letter, or entitlements to time and money are forfeited. 

 

 

 

Dissatisfactions and disputes

 

 

The NEC sets out a detailed procedure under the Y(UK)2 Addendum. If dissatisfied with an action or inaction by the other party, then the aggrieved party has only four weeks after becoming aware, in which to notify dissatisfaction. Otherwise, he loses his rights.  Within two weeks of the notice, the parties meet and attempt to resolve the matter. No dissatisfaction can become an adjudicable dispute unless the matter is still unresolved four weeks after the issue of the notice.

 

 

In practice, this means that if the subcontractor is dissatisfied with the contractor’s response to his early warning or compensation event notice, or if the contractor  does not respond at all, the subcontractor must give notice of dissatisfaction within four weeks  or risk forfeiting his entitlements.   Since one of the most common problems is the contractor ignoring the subcontractor’s notices,  it is essential that notices and response times etc are recorded and monitored with the utmost diligence.

 

 

 

Procurement routes

There are several procurement options available to the end client and contractor. The three chief options are listed below.

 

 

Option “A” – Priced subcontract with activity schedule.

 

This option is based upon a detailed programme with matching priced activity schedule. The subcontractor can claim payment only for completed activities. Unfixed materials are not paid. Cash flow is adversely affected and finance charges need to be allowed in the tender.

 

 

Option “B” – Priced subcontract with bill of quantities.

 

This option is more like a traditional measure and value contract. Cash flow is better, although unfixed materials are not paid.

 

 

Option “C” – Target subcontract with activity schedule

 

In this option,. the tender is submitted on the same basis as Option “A”, and this becomes the target, but the subcontractor is paid his actual costs (subject to disallowances and audit).  At the end of the job, the total costs are compared with the target (after adjustment for compensation events) and there is a share out of “pain or gain” on a pre-stated basis. In practice, the percentages are likely to be set so that the subcontractor suffers 100% pain on all overspend and perhaps 50% of gain.   Disadvantages are that the subcontractor cannot apply for payment of his costs until he can prove he has actually paid them out.  Also, in event of overspend, he may have to find a substantial sum in repayment of “pain” at the end of the job.   Option “C” implies severe cash flow deficit for any subcontractor, and this needs to be reflected in the tender price.

 

 

 

Conclusion

 

As stated at the outset, there are advantages in the NEC for all concerned. Financial control is greatly improved. End of job disputes are minimised.  However, the subcontractor must allow in his tender for the increased staff to comply with the rigid rules, in particular, planning and quantity surveying resources.   Above all,  it is vital to comply with the requirements for early warnings and compensation events, and to give notice of dissatisfaction within the prescribed period. Otherwise, all entitlements may be lost for ever.

 

 

 

Back to Jack Russell Home page.

 

Back to Jack Russell column Contents page for many more such articles.

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk

 

 

 

(This article is based on the “Jack Russell” contract law column in the July 2005 “Electrical Times”).