John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk

“Jack Russell” of the  Electrical Times and author of “The Streetwise Subbie”

 

 

 

LOSS AND EXPENSE

 

 

RECOVERING PROLONGATION COSTS

 

 

 

When the sub-contractor over-runs his  completion date, he risks  incurring damages from the client and/or main contractor.  He also incurs his own costs of “prolongation”,  because he has to retain his site establishment, engineers and supervisors, plant etc beyond the period allowed in his tender.  If the sub-contractor  has submitted regular  delay notices, he should be able to secure an extension of time and protection from damages.  Recovery of his over-run costs may be more difficult. 

 

 

 

Prolongation costs

 

These costs are often called “preliminaries”, and the client will demand a  tender breakdown, with the object of pricing the over-run based on the tender allowances.  Such requests should be resisted. The general position is that the delay is to be  based on actual costs incurred at the dates when the actual delays occurred.  This may well lead to a series of   calculations based on “full strength” prelims, rather than at  the reduced “tail end”.

 

On bigger jobs, an effective approach is  a bar chart showing  originally planned staff resources (eg site manager, engineers, supervisors, charge-hands, surveyors, planners, clerical staff, first aid and welfare, storekeeper , watchmen, cleaners and canteen staff etc)  with the specific duration in weeks for each individual. Underneath each “bar” the chart will then show the “actual” resource used and duration of same. This  has the added benefit of picking up additional staff resources introduced in response to  the events imposed upon  progress.

 

If  added  difficulty of the job necessitates increases in staff and/or supervisory involvement, then this should be notified at the time, specifying  exact reasons for the increase, the proposed duties of the personnel concerned and  intention to seek reimbursement. It is  wrong to leave this sort of claim until the end, as so many claimants do.

 

 

 

Off site overheads

 

Wherever possible, off site  personnel such as contracts managers  should be costed into the claim on the basis of actual involvement during the period of delay.  The  chances of recovery can be enhanced by “job costing” as many  head office personnel as is possible. This involves all head office personnel completing weekly time sheets by allocation to specific projects, to be  costed against the various projects on an hourly or daily rate.  This “job costing” approach is of tremendous assistance in substantiating claims for weekly cost of head office personnel due to  over-run. Also,  it has the added benefit of reducing the residual percentage left  to cover fixed overheads (eg Directors, administrative and ancillary staff, lease/rent of premises, rates, heating and lighting, office equipment,  etc).

 

As to these  residual (fixed) overheads,  the more acceptable approach is  to add a  percentage  to the net total of the claim. This percentage may be verified by a letter from the company’s auditors and/or reference to  trading accounts.

 

More ambitious is a “formula”  approach.   In simplest terms, the formula is as follows :  H/100 x c/cp x pd  (where H = head office percentage from tender (Hudson) or company accounts (Emden),  c = contract sum, cp = original contract period, and pd = period of delay).

 

Any formula type claim must make  allowance for additional overheads recovery via variations.  Also, the claimant would need to prove availability of other work during the period of  prolongation, plus evidence of  turning  work away due to staff being tied up on the delayed project. He may well be challenged to open his company books and prove the tender overheads, or those arising in  trading accounts, and  to demonstrate an under recovery of overheads during the period in question. These are tall hurdles, but if the claim is genuine,  not insurmountable.

 

 

 

Loss of profit

 

This may be valid in principle, but subject to similar difficulties as  overheads.   In both cases, the claim is  hard to prove in times of recession, when profitable work  may be hard to find.  Also,  the claimant would have to prove that he was capable of earning profit on his trading generally. 

 

 

 

Increased costs (fluctuations) due to fixed price shift

 

On a fixed price job, delay may incur expenditure due to wage increases and/or materials price rises.  The easier approach is to assess  the additional costs by reference  to industrial   indices.  However, the client may insist on full details of each operative and invoice etc.

 

 

 

Notices and records

 

It is absolutely vital to submit written notices when  any significant delay becomes likely, and to request extension of time when the original completion date appears threatened .  The same applies to claims for loss and expense. These notices must be supported by site records such as diaries, progress reports, updated programmes, etc.   It is far better to address  the problem by proactive notice and discussion than to become locked in a dispute after the project is completed.

 

 

Home page