EXAMPLES OF SITE RECORDS

 

 

 


 

 

 

 

 

 

 

 

 

 

 

 



                                 SITE DIARY                   Ref No  1344

 

 

CONTRACT:......Redhill  Hospital..............................................DATE:   8 April ...........1995.....

 

WEATHER:             Fine all day                    VISITORS:        Mr Graham Jones,  Mr L Hibbs, (Hd office)

                                                                             Mr Tucker (Architect)

PERSONNEL ON SITE

 

SUPVSRS...1.......FMN....1.....C/HDS....2.......APPVD ELS.....4....ELS ....22  APPCES.....4...  .LABS... 4..........OTHERS.....Driver ..1,   Site Clerk...1,    Site Secretary....1.

 

SUB-SUB-CONTRACTORS (EG CABLE GANGS, FIRE ALARMS SPECIALISTS ETC):

 

Smith Brothers (Cablers).....1 Fmn,  6 operatives

High Tek  (PA specialists)....1 Fmn, 2 operatives

 

AREAS/ ACTIVITIES STARTED TODAY:

 

Block C  Level 1 -  1st fix

Block A  Level 6 Plant room - 1st fix 

Block B  Level 5 - 3rd fix

 

AREAS/ACTIVITIES COMPLETED TODAY:

 

Block A Level 4 - 1st fix

Block B Level 4 - 3rd fix

 

MAIN PROGRESS TODAY(Other than starts/completions):

 

Block A -    Levels 1 and 2 - 1st fix

Block B -     Levels 1 and 2- 2nd fix/final fix

Block E -    Levels 1 and 2 - 2nd fix/final fix  

 

VARIATIONS/INSTRUCTIONS RECEIVED TODAY:

 

SI No 56  recvd from Builder  - Cancel Type A luminaires for Block A (pending Archt’s review).

AI No 124 recvd from Bldr   -  Changes to lighting for Block G.

 

CURRENT DELAYS DUE TO ACCESS/BUILDING WORKS/ OTHER TRADES:

 

Block G still unavailable - roof not completed

Block A Level 1 Rooms 45 - 54 still full of scaffolding - prevents 1st fix

 

 

CURRENT DELAYS DUE TO INFORMATION/DRAWINGS/VARIATIONS:

 

Still await Archt’s decision re X Ray equipment for Block A .

Approvals still awaited re working dwgs for Block B Sub basement SW Room.

 

OTHER EVENTS:     Ray Holmes fell off ladder in Block A L1 Rm 72. Hurt ankle. Took to hospital and then home. See separate official report and Safety Register.

 

 

SIGNED:     R Goodguy                   TITLE: Site Supervisor

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                   

SITE  DELAY REPORT                Ref 2475

 

 

Contract:   Redhill  Hospital                                                 Date:    8 April 1995

 

To:                        Mr J Bloggs

                 Ace Builders Ltd

 

 

 

Re:

Block/Level/ Area/Room :                       Block A Level 1 Rooms 45 - 54

 

Activity:                Electrical 1st fix  (Prog Activity A/24)

 

 

We respectfully report the following event, which is delaying our progress :

 

Rooms 45 - 54 still full of scaffolding, which continues to prevent us from starting Electrical 1st fix.  Please see our notices  dated  11/3/95, 18/3/95, 25/3/95 and 31/3/95.

 

 

 

Action/information required to enable progress :

 

Please can you clear for access  urgently, as promised by your Mr Potter on 1/4/95.

 

 

 

 

Delay to programmed activity :

 

Prog Activity A/24 shows commencement of Electrical 1st fix in Block A on 11/3/95

 = 4 weeks delay ongoing.

 

 

 

 

Effect of Delay:

 

Rooms 45,46, 47 are main plant rooms and critical to electrical progress in Block A and project generally.  Any delay will “knock on” directly to overall programme completion date of  6 July 1995.

 

 

 

Signed:     R  Goodguy                   Title:    Site Supervisor 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TECHNICAL QUERY REGISTER

 

TQ No

DATE

SUBJECT

REPLY REQUD

REPLY RECVD

DATE RESOLVED

 

 

 

 

 

 

1

1/2/95

SW rooms A -45/47

Panel positions

8/2/95

2/3/95

2/3/95

2

6/2/95

Block B Lighting scheme

13/2/95

20/2/95

See 2A

3

14/2/95

Block C Cable spec

21/2/95

21/2/95

21/2/95

2A

21/2/95

Block B Lighting scheme

28/2/95

7/3/95

See 2B

4

3/3/95

SW rooms wiring

10/3/95

10/3/95

10/3/95

2B

7/3/95

Block B Lighting scheme

9/3/95

12/3/95

12/3/95

5

15/3/95

Block A Level 1  X Ray equipment

22/3/95

23/3/95

See 5A

6

22/3/95

Fire Alarms specification

29/3/95

25/3/95

See 6A

5A

23/3/95

Block A Level 1 X Ray equipment

24/3/95

26/3/95

See 5B

6A

25/3/95

Fire Alarms specification

27/3/95

27/3/95

27/3/95

7

28/3/95

PA wiring generally

10/4/95

 

 

5B

3/4/95

Block A Level 1 X Ray equipment

5/4/95

5/4/95

5/4/95

8

7/4/95

Block H Level 3 Path Lab lighting

17/4/95