EXAMPLES OF SITE RECORDS

SITE
DIARY Ref No 1344
CONTRACT:......Redhill Hospital..............................................DATE: 8 April ...........1995.....
WEATHER: Fine all day VISITORS:
Mr Graham Jones, Mr L Hibbs, (Hd office)
Mr
Tucker (Architect)
PERSONNEL ON SITE
SUPVSRS...1.......FMN....1.....C/HDS....2.......APPVD ELS.....4....ELS
....22 APPCES.....4... .LABS... 4..........OTHERS.....Driver
..1, Site Clerk...1, Site Secretary....1.
SUB-SUB-CONTRACTORS (EG CABLE GANGS,
FIRE ALARMS SPECIALISTS ETC):
Smith Brothers (Cablers).....1 Fmn, 6 operatives
High Tek (PA specialists)....1 Fmn, 2 operatives
AREAS/ ACTIVITIES STARTED TODAY:
Block C
Level 1 - 1st fix
Block A
Level 6 Plant room - 1st fix
Block B
Level 5 - 3rd fix
AREAS/ACTIVITIES COMPLETED TODAY:
Block A Level 4 - 1st fix
Block B Level 4 - 3rd fix
MAIN PROGRESS TODAY(Other than starts/completions):
Block A - Levels 1 and 2 - 1st fix
Block B - Levels 1 and 2- 2nd
fix/final fix
Block E - Levels 1 and 2 - 2nd fix/final fix
VARIATIONS/INSTRUCTIONS RECEIVED TODAY:
SI No 56 recvd from Builder - Cancel
Type A luminaires for Block A (pending Archt’s review).
AI No 124 recvd from Bldr -
Changes to lighting for Block G.
CURRENT DELAYS DUE TO ACCESS/BUILDING
WORKS/ OTHER TRADES:
Block G still unavailable - roof not
completed
Block A Level 1 Rooms 45 - 54 still full
of scaffolding - prevents 1st fix
CURRENT DELAYS DUE TO
INFORMATION/DRAWINGS/VARIATIONS:
Still await Archt’s decision re X Ray
equipment for Block A .
Approvals still awaited re working dwgs
for Block B Sub basement SW Room.
OTHER EVENTS: Ray Holmes fell off
ladder in Block A L1 Rm 72. Hurt ankle. Took to hospital and then home. See
separate official report and Safety Register.
SIGNED: R Goodguy TITLE: Site Supervisor
Contract: Redhill
Hospital Date: 8 April 1995
To: Mr J Bloggs
Ace
Builders Ltd
Re:
Block/Level/ Area/Room : Block A Level 1
Rooms 45 - 54
Activity: Electrical 1st
fix (Prog Activity A/24)
We respectfully report the following
event, which is delaying our progress :
Rooms 45 - 54 still
full of scaffolding, which continues to prevent us from starting Electrical 1st
fix. Please see our notices dated
11/3/95, 18/3/95, 25/3/95 and 31/3/95.
Action/information required to enable
progress :
Please can you clear for access urgently, as promised by your Mr Potter on
1/4/95.
Delay to programmed activity :
Prog Activity A/24 shows commencement of
Electrical 1st fix in Block A on 11/3/95
= 4 weeks delay ongoing.
Effect of Delay:
Rooms 45,46, 47 are main plant rooms and
critical to electrical progress in Block A and project generally. Any delay will “knock on” directly to
overall programme completion date of 6
July 1995.
Signed: R Goodguy Title: Site Supervisor
|
TQ No |
DATE |
SUBJECT |
REPLY REQUD |
REPLY RECVD |
DATE RESOLVED |
|
|
|
|
|
|
|
|
1 |
1/2/95 |
SW rooms A -45/47 Panel positions |
8/2/95 |
2/3/95 |
2/3/95 |
|
2 |
6/2/95 |
Block B Lighting scheme |
13/2/95 |
20/2/95 |
See 2A |
|
3 |
14/2/95 |
Block C Cable spec |
21/2/95 |
21/2/95 |
21/2/95 |
|
2A |
21/2/95 |
Block B Lighting scheme |
28/2/95 |
7/3/95 |
See 2B |
|
4 |
3/3/95 |
SW rooms wiring |
10/3/95 |
10/3/95 |
10/3/95 |
|
2B |
7/3/95 |
Block B Lighting scheme |
9/3/95 |
12/3/95 |
12/3/95 |
|
5 |
15/3/95 |
Block A Level 1 X Ray equipment |
22/3/95 |
23/3/95 |
See 5A |
|
6 |
22/3/95 |
Fire Alarms specification |
29/3/95 |
25/3/95 |
See 6A |
|
5A |
23/3/95 |
Block A Level 1 X Ray equipment |
24/3/95 |
26/3/95 |
See 5B |
|
6A |
25/3/95 |
Fire Alarms specification |
27/3/95 |
27/3/95 |
27/3/95 |
|
7 |
28/3/95 |
PA wiring generally |
10/4/95 |
|
|
|
5B |
3/4/95 |
Block A Level 1 X Ray equipment |
5/4/95 |
5/4/95 |
5/4/95 |
|
8 |
7/4/95 |
Block H Level 3 Path Lab lighting |
17/4/95 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|