VARIATIONS – DON’T WORK FOR FREE !

 

 

 

*   Get all instructions confirmed in writing before spending your money.

 

*   Check at the outset exactly who is authorised to  issue instructions to you.

 

*   Check at the outset exactly who is responsible for your payments.

 

*   Don’t spend money on the instructions of “Little Tin Gods” (ie people with a lot to say but no contractual authority).

 

*   Don’t be fooled by the “PQS” excuse (eg “the PQS has been too busy to look at your variations prices  etc”).  Your contract is with the builder – NOT the PQS. Check your subcontract conditions. The PQS is unlikely to be mentioned. So insist that the builder addresses your variations as a matter of urgency.

 

*   Don’t use the bill of quantities as a shopping list – remember that you are entitled  to a varied rate if the character and/or conditions of the work changes.

 

*   Remember that JCT 98 and DOM/1 etc allow you to re-price original contract works where you can show that the character and/or conditions have been affected by variations.

 

*   Include additional prelims expenditure in your variations prices where appropriate.

 

 

 

VALUATION OF VARIATIONS

 

 

Improve your cash flow

Grasp your entitlements to “star rates”

Don’t accept bill rates for varied work

 

 

Most Contract Conditions contain provisions whereby varied work, and/or contract work affected by variations, qualifies for a revised rate if it can be demonstrated that the work has changed in character and/or conditions from that reasonably apparent from the original contract documents. 

 

In practice, most Client's Quantity surveyors tend to overlook these provisions and prefer to use the original Bill or Schedule rates rather like a "Shopping List".  This is not the correct approach.  However, the initiative, in practical terms, must rest with the Contractor and/or Sub-contractor.  Leading  text books emphasise that, in reality, a substantial proportion of works carried out under variations do qualify for re-rating! 

 

Appended is a "Check List" summarising factors which may be reasonably argued as   having changed  the original character and/or conditions of the work:

 

It may be seen from the  list, which is by no means exhaustive, that a substantial proportion of variations in fact require re-rating to reflect the changed character/conditions.  Equally, it is possible to show that areas of original contract work have been similarly affected by variations.

 

By maximising these avenues during the currency of the works, it is possible to expedite cash flow and to minimise the overspill  balance of disruptive costs  remaining to be processed through the medium of a formal Loss and Expense Claim.

 

 

********************

 

 

CHECK LIST OF POSSIBLE FACTORS CHANGING CHARACTER/CONDITIONS.

 

 

*   Winter working.

*   Excessive number of instructions.

*   Late and/or "piecemeal" receipt of same.

*   Issue of variations in disregard of agreed programmes.

*   Immediate/short notice response required to instructions.

*   Special procurement, planning, supervision arrangements.

*   Loss of trade discounts due to  purchase of small quantities of materials.

*   Extra costs due to transport and handling of ditto.

*   Increased costs (fluctuations) on labour and materials.

*   "Piecemeal working" in disregard of programmed sequences.

*   Special return visits to areas in order to execute small quantities of work.

*   Special isolation of individual electrical circuits in energised areas.

*   Special return visits by Sub-subcontractors.

*   Special hire and/or retention of plant and access  equipment.

*   Additional builder's work.

*   Re-familiarisation on return to completed areas.

*   Working in exceptionally congested circumstances due to out of

*   sequence working.

*   Re-testing and commissioning.

*   Working in areas which have been occupied by Employer

*   Working out of normal hours.

*   Obtaining access permits for return visits to occupied areas.

*   Detours around site to gain access to obstructed areas

      e.g. blocked stairways etc).

 

 

 

Keynote:         

Don't use the Bill of Quantities as a "shopping list".

 

 

John Russell  

Contracts & Training Consultant

Cheshire CW4 7DP

Tel:  07770 986444

Email: swsubbie@globalnet.co.uk

Website: jrc0nsultant.co.uk

 

 

Back to home page

 

Back to top

 

 

END OF “VARIATIONS”