DELAYS AND ENTITLEMENTS – TAKE THE YES/NO TEST FOR
M&E SUBBIES – SUGGESTED ANSWERS.

|
Ref |
REASON FOR DELAY |
EOT? |
COSTS? |
|
|
|
|
|
|
1 |
Our fire alarms subbie is tied up on a big
job in Scotland. |
NO |
NO |
|
|
|
|
|
|
2 |
The plant rooms have not yet been made
waterproof, bricklayers and roofers still working. |
YES |
YES |
|
|
|
|
|
|
3 |
Architect very late in issuing CCTV information, which we have requested on
many occasions. |
YES |
YES |
|
|
|
|
|
|
4 |
Builder’s own mechanical subbie late with
his plant. We had to leave cables looped until ready, then return. |
YES |
YES |
|
|
|
|
|
|
5 |
Big variation to lighting scheme issued to
us only one week before completion date |
YES |
YES |
|
|
|
|
|
|
6 |
We could not get materials from Newey Eyre
because we are “on the stop” |
NO |
NO |
|
|
|
|
|
|
7 |
It has been the wettest July in history |
YES |
NO |
|
|
|
|
|
|
8 |
The client was very late in providing “free issue” equipment which we requested
in good time |
YES |
YES |
|
|
|
|
|
|
9 |
Architect issued late instructions re provisional sums. We had
included this on our procurement schedule at start of job, six months ago but
not since. |
NO |
NO |
|
|
|
|
|
|
10 |
Bricklayers on strike for 4 weeks. |
YES |
NO |
|
|
|
|
|
|
11 |
Builder issued revised programme showing
project end date put back 4 weeks |
NO |
NO |
|
|
|
|
|
|
12 |
Ceilings subbie walked off site for 2 wks for
non payment. Our final fix was delayed. |
YES |
YES |
|
|
|
|
|
|
13 |
Very frosty during February, delays to our
car park lighting. |
NO |
NO |
|
|
|
|
|
|
14 |
Architect issued over fifty AI's (variations)
in last 3 weeks of job, causing us general delay. |
YES |
YES |
John Russell
Construction Contracts & Training Consultants
(Established 1984)
Cheshire CW4 7DP Tel : 07770 986444
Email :
swsubbie@globalnet.co.uk Website:
www.jrconsultant.co.uk
“Jack
Russell” of the Electrical Times and author
of “The Streetwise Subbie”