DELAYS AND ENTITLEMENTS – TAKE THE YES/NO TEST FOR M&E SUBBIES  SUGGESTED ANSWERS.

 

 

 

Ref

REASON FOR DELAY

EOT?

COSTS?

 

 

 

 

1

Our fire alarms subbie is tied up on a big job in Scotland.

NO

NO

 

 

 

 

2

The plant rooms have not yet been made waterproof, bricklayers and roofers still working.

YES

YES

 

 

 

 

3

Architect very  late in issuing CCTV information, which we have requested on many occasions.

YES

YES

 

 

 

 

4

Builder’s own mechanical subbie late with his plant. We had to leave cables looped until ready, then return.

YES

YES

 

 

 

 

5

Big variation to lighting scheme issued to us only one week before completion date

YES

YES

 

 

 

 

6

We could not get materials from Newey Eyre because we are “on the stop”

NO

NO

 

 

 

 

7

It has been the wettest July in  history

YES

NO

 

 

 

 

8

The client was  very late in providing “free issue” equipment which we requested in good time

YES

YES

 

 

 

 

9

Architect issued late  instructions re provisional sums. We had included this on our procurement schedule at start of job, six months ago but not since.

NO

NO

 

 

 

 

10

Bricklayers on strike for 4 weeks.

YES

NO

 

 

 

 

11

Builder issued revised programme showing project end date put back 4 weeks

NO

NO

 

 

 

 

12

Ceilings subbie walked off site for 2 wks for non payment. Our final fix was delayed.

YES

YES

 

 

 

 

13

Very frosty during February, delays to our car park lighting.

NO

NO

 

 

 

 

14

Architect issued over fifty AI's (variations) in last 3 weeks of job, causing us general delay.

YES

YES

 

Home

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk

“Jack Russell” of the  Electrical Times and author of “The Streetwise Subbie”