BEWARE OF UNPAID ACCELERATION

 

Most sub-contractors will be familiar with the pressures from the client or main contractor as the project nears its planned completion date.  Having been constantly delayed by lack of information and necessary access to work faces, a “delayed bulge”  of information and access is  made  available.  The sub-contractor is told that the completion date must be met, and reminded of his duties under "best endeavours".  Threats of damages for non-completion are received.

 

The sub-contractor is now in a very difficult position.  Very often, the only measures open to him are to increase his labour force and/or work weekends. 

However, such strategies can prove very costly indeed.  What is the true contractual position?

 

“Best endeavours" is an important obligation which features in many contracts. It involves a proactive willingness to rearrange activities, and to make all reasonable efforts to prevent or reduce the delay.  However, most text books suggest that this should not involve substantial expenditure. 

 

If the delay is the fault of the sub-contractor, he may well consider it  less costly to use “special measures” than to incur damages and set off for failure to complete on time.  If he has been careless in submitting delay notices, or has signed up to a contract with a “beck and call” clause, he may be in a weak position which leaves him little option. 

However, assuming that the project delays are not his responsibility, and he has protected his position as to extension of time,  he usually has no contractual obligation to spend resources and money to overcome delays caused by others.

 

In practice, such cases usually constitute "hidden acceleration".   Those contract forms which recognise acceleration usually provide for prior agreement and/or formal instructions, with specific arrangements for reimbursement.  In other cases, (ie JCT98 and DOM/1 etc)  no provisions exist and acceleration then stands to be discussed as "equal parties" outside the contract.

 

In response to the usual attempts at coercion, the sub-contractor should resist the temptation to “knee jerk”.  He should remain calm and professional, and remind the main contractor  as to the origins of the delay, and the sub-contractor's entitlements to extension of time.  The  nature and range of possible "special measures" should be discussed, together with basis of payment. This may be a "lump sum" or series of "milestone payments",  perhaps a "formula" basis of premium time with a percentage to cover overheads and profit, additional supervision and labour costs.  This may well be the time to seek a “wrap up deal” to resolve all existing contractual issues.  It is essential to include  a list of provisos, with precise requirements in terms of necessary access, information and instructions.

 

It is vital to achieve and record the precise terms of the agreement before embarking on the expenditure.  Terms such as  "reimbursement of reasonable costs" are virtually meaningless.  All too many sub-contractors have learned this the hard way.

A common mistake is to expend the resources, and claim retrospectively for costs of “constructive acceleration”, on the basis that the main contractor’s failure to issue an extension of time left the sub-contractor no option but to accelerate.  Such a strategy is fraught with difficulty, and seldom succeeds. Once the sub-contractor has served his purpose, there will be little sympathy from other parties.

 

The financial implications of acceleration can be massive, and this needs to be fully considered before commencement of any such measures.  As to overtime working, a seven day week involves premium payments, and results in fatigue,  reducing productivity by approximately 20%, worsening with each week it continues. 

 

An increased labour force involves importation and incentive costs.  As density of labour increases, so does congestion of workfaces , particularly if other trades are working under similar conditions.  Supervision, co-ordination and control become much  harder.  The common tendency to increase labour without comparable increases in supervision exacerbates the situation.      Use of weekend labour from other sites involves premium payments and lack of job knowledge, also absence of project commitment.

 

Use of a "shift" system will often  result in wasteful “hand over”  time for both men and supervisors.  Accelerated working may actually cause an increase in absenteeism during the normal week, operatives having earned double time at the weekend.  Interruptions lasting more than half an hour have been proved to  cause a productivity  loss throughout the remainder of any disrupted day.

 

In conclusion, any sub-contractor who embarks upon any form of acceleration, without a satisfactory written agreement, is unlikely to recover his costs.

 

 

 

Home.htm

 

 

 

 

John RUSSELL BI-MONTHLY SERIES

ARTICLE NO 11

DATED 5/10/02

FOR END OF OCTOBER 2002  “TIMES”

FILE biet11

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk