BEWARE "STARTING THE CLOCK ".

 

Starting work on a sub-contract  "sets the clock ticking" and the agreed on site working period begins to elapse.  At the end of that period, if the sub-contractor’s  works are incomplete (and in the absence of a formal extension of time), he could be liable to massive financial "damages" from the client and/or main contractor.  Contrary to the popular misconception, there is no need to prove that the sub-contractor is “guilty” of delay.  On the contrary, the onus is entirely upon the sub-contractor to request and demonstrate entitlement to an extension of time. If he is unsuccessful in this regard, then the period of sub-contract over-run will trigger off deduction of damages from payments otherwise due under the sub-contract.

 

So, what are the "streetwise" angles on "commencement?  Most sub-contract conditions provide for the main contractor to give written notice of one or two weeks, instructing the sub-contractor as to  formal commencement date.  Unfortunately, this requirement is often ignored and the sub-contractor tends to drift gradually onto site in a rather casual manner.   In short,  many sub-contractors fail to realise the vital importance of establishing and recording the actual date of their commencement on site and the eventual achievement of  practical completion and just “let it happen”. 

 

Building not ready?  A sub-contractor  who commences on an "unready" site puts himself at great disadvantage and risk!  Having commenced, he will find himself  "working out of sync" with the other trades.  Then, when the main contractor finally "gets his act together"; the sub-contractor  is accused of "delaying handover"!

 

A sub-contractor  must visit and inspect the site well in advance of the planned start date.  If the site clearly will not be "ready", then record it with the specific reasons, by writing to the main contractor. Take photographs.   Be aware that "uneconomic working conditions" are not a valid reason for delayed commencement.  That aspect has to be dealt with by way of subsequent extension of time and/or loss and expense.

 

If a deferment of site start  is mutually agreed, then record the agreement in writing, including the date of the conversation and the name of the client’s or main contractor’s representative involved  and confirm the sub-contractor’s  entitlement to a revised completion date (based upon the original agreed period commencing at the new start date).  Whether the sub-contractor has to request an "extension" will depend on the particular sub-contract conditions. 

 

If the main contractor, despite the sub-contractor’s  protests, still gives  formal "notice to commence", then (providing the site is safe for working), the sub-contractor probably has to comply.  Again, it all depends on the precise sub-contract terms.  If the sub-contractor then finds himself "delayed from the start" (i.e. by lack of access and/or building readiness etc), he will have to give a formal delay notice as at "day one" and continue to do so for as long as the delays continue.

 

The sub-contractor must also be aware that the action of commencing work will usually denote “acceptance of conduct” of the main contractor’s order and any terms and conditions attached thereto, however onerous the latter may be.   So, if the sub-contractor is unhappy with any aspect of the main contractor’s order, he should endeavour to resolve matters before commencing work. Afterwards is too late!

 

Many sub-contractors of my acquaintance have found, to their cost, that sending "two men and a dog" to do a couple of days work on an unready site has subsequently been held to have "started the clock ticking" (ie triggered off the sub-contract period).   So, do you refuse to co-operate?  Most certainly not!  What the sub-contractor should do is to cover himself with a nice polite letter which confirms that the sub-contractor’s  action in visiting site for this pre-start work is purely to assist the main contractor, is not to be construed as formal commencement of the sub-contractor’s  works and is "without prejudice” to the sub-contractor’s  contractual entitlements.

 

Similar advice applies to the recording of practical completion of the sub-contract works.  This latter date is most important, since it places a stop limit to the further imposition of damages for delay and denotes the commencement of the formal defects period. Also, this is the time to request the release of the first half of the sub-contractor’s retention monies.   In fact, Clause 14.1 of the most popular form of sub-contract (DOM/1) actually states that if the sub-contractor submits his opinion in writing that he has now achieved practical completion and the main contractor fails to state otherwise within fourteen days, then practical completion shall be deemed to have taken place on the date so notified.

 

In conclusion, the “streetwise subbie” should always take great care to see that the actual  commencement date is clearly agreed and recorded in writing, and likewise the actual date of practical completion.  During his presence on site, all delays should be notified in writing to the main contractor and, in the event of a likely over-run of the original sub-contract period then an extension of time should be promptly requested. These simple measures are well within the capability of any reputable sub-contractor, and  yet will produce great benefits in terms of protection.

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

“Contract law” column for Electrical Times –

 published 1 Sept 05.

 

Home.htm

Jack Russell column.htm