CHECK THAT ORDER

 

SUBBIES SHOULD CHECK THE  ORDER BEFORE PROCEEDING

 

 

In our last article, we looked at the pitfalls involved in the tendering process. In this issue we  consider the streetwise steps in checking a letter of intent and official order from the client or builder.

 

Letters of intent

 

The letter of intent is a main source of subsequent problems.  Such letters are often  worthless.  Ideally, the subbie should look for :

 

·       Clear and unqualified acceptance in writing of the  tender

(In this case, the letter would usually create a binding contract)

 

·       Confirmation of price, and allied terms

 

·       Confirmation of programme, dates and periods

 

·       Confirmation of terms and conditions

 

 

At the very least, the subbie must require:

        

 

o       Instruction to proceed and/or expend money on specific functions (eg. commence working  drawings and procurement of quotations for specialist items")

 

o       Definite promise to pay for all works and/or services provided up to a stated value,  in the event of the subcontract not proceeding.

 

o       Absence of “counter offers” and “additional conditions”

 

Many projects start off on a vague basis, with glaring omissions as regards price, programme and/or other terms.  These deficiencies are the seeds of subsequent dispute. Some temporary protection can be engineered by a carefully framed reply.  However, it is dangerous  to expend substantial resources in the absence of a clear agreement. In essence, all letters of intent should be treated with great caution.

 

 

Receipt of order and/or subcontract agreement

 

The subbie must check that the value, programme, details and conditions are those on which the tender was based and/or subsequent agreements reached.   Check the small print on the reverse of the order.  This is where clients and builders  hide their onerous clauses.

 

Beware the  client or builder who smuggles in his own payment  or "set off" clauses even though standard terms have been agreed.  Refusal to sign and return the acknowledgement slips cannot be relied upon as evidence of non-acceptance.   Any “act” taken on the order can be construed as “acceptance by conduct”.

 

 

Acceptance of order or terms "by conduct"

 

Many subbies unintentionally accept onerous terms of an order by commencing on site before terms are agreed.  This can be taken as  “acceptance by conduct" even though negotiations are still in progress.  The subbie must protect his position by a suitably framed letter (eg.  "Without Prejudice to our contractual position etc"). If you have to start work without agreed terms, make this  clear in writing, stating your position  regarding outstanding matters.  However, you may still be at risk, despite this precaution.

 

 

Offer and  counter – offer  -  the "battle of the forms'

 

When the builder accepts the subbie's quotation "in accordance with our standard terms" he actually makes a "counter offer" which  supersedes the terms of the original tender.  If the subbie commences work without dissent, his action may well  denote “acceptance by conduct”.  This can also be so where work is commenced with correspondence still passing to and fro. This is sometimes called “battle of the forms”.

 

 

Quantum meruit

 

If the subbie does start work, having confirmed his disagreement,  there may well be no valid contract at all, and any work done may have to be valued on a “quantum meruit”  basis.

The  term  “quantum meruit”  means "what it is worth".   This is not to be confused with "cost plus", but means a reasonable sum of money for work done in good faith, but where there is no valid contractual agreement. This sometimes arises from work done on a letter of intent basis,  where that letter was insufficient to constitute a binding  agreement. Nevertheless, the subbie is entitled to some reasonable payment.

 

 

Retrospective agreement

 

The formal  document will have retrospective effect once signed. The conditions  then apply retrospectively to works which have already taken place on site, as though the agreement had been signed on "day one".

 

This can be fraught with problems. Frequently, the works have become subject to delays, claims and variations during the  period whilst the agreement remains incomplete.  One party may wish these events to be reflected in the formal agreement. This should not really be the position. What should, in theory, apply is that claims, delays and variations should be dealt with under the terms of the eventual agreement,  as if that agreement had been in force all along.

 

 

Incorporation of terms

 

The order will often make reference to a set of terms and conditions (be they standard, such as DOM/1,  or otherwise) which do not physically appear in the formal documentation.  In such a case, the terms and conditions will usually govern the conduct of the parties just as if they had been physically "signed and bound in".

 

Starting off on the right foot

 

In the next article, having negotiated the initial pitfalls,  I will give some streetwise tips for “starting off on the right foot”.

 

 

 

Back to Jack Russell Column Contents

 

Back to home page

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk