PROGRAMME PITFALLS

 

A sub-contract without an agreed programme is built on “shifting sand”

 

 

 

The contractual baseline

 

 

Most  standard  sub-contracts for use with JCT forms require the sub-contractor to carry out  his work in accordance with the details set out in the tender or sub-contract appendix and “reasonably in accordance with the progress of the main contract works".  If the appendix refers to a specific programme, the sub-contractor will be contractually bound to perform in accordance with that programme.

 

The sub-contractor must try to get an agreed programme incorporated by reference within this original agreement. The next best thing is to refer to the sub-contract requirements as set down within the original main contract programme.   The full title, date and reference number of the programme must be quoted.  Vague allusions to "the main contract (or sub-contract) programme" are of little help.

 

Many main contractors prefer  to treat the sub-contractor as a totally flexible resource.   They will insert  terms such as "work in accordance with the contractor's instructions" or " to suit main contract progress”.   There is case law which emphasises  that any sub-contractor who accepts  such terms agrees  to be delayed and disrupted without reimbursement.

 

If the sub-contractor has managed to get a detailed programme incorporated in his documents, then that programme must be carefully retained, since it is "the contractual baseline" for monitoring  delays, extensions of time, loss and expense etc.

 

 

Shifting sand

 

 

Where the original documents mention no specific programme, then the sub-contractor must   improve the situation by obtaining the main contractor's requirements and submitting/agreeing a detailed sub-contract programme before work commences.   This must  be confirmed in writing to the main contractor (ie title, date and programme number).  The covering letter should  emphasise that this represents the original sub-contract programme as agreed between the parties.    Remember, a sub-contract  without an agreed programme  is built on “shifting sand”.

 

A sub-contractor who takes a job on the basis of a "period of time" with no programme details could be placed in an onerous position, since he has no baseline against which to demonstrate his case for extension of time and/or financial reimbursement.

  

Having achieved a “baseline” programme, any significant changes may well  bring  entitlement to compensation in time and money.  This must not be taken to extremes,  since the sub-contractor must always use his "best endeavours".  However, this obligation is not thought to involve substantial additional expenditure. 

 

 

Target programmes

 

 

The main contractor may  propose, prior to commencement,  that the sub-contractor should work to a "target programme" of reduced  duration.  The sub-contractor can either  treat the proposal as an "acceleration" and submit a price for negotiation, or he can co-operate on the basis of "goodwill".

 

In either case,  it is essential that the "ground rules" are clearly agreed and confirmed.  I have seen sub-contractors levied with "delay costs" because they failed to achieve a "target programme".  If co-operating, then state in writing that your co-operation, and the status of the "target programme" is on the basis of "best endeavours" and is "without prejudice" to your contractual entitlements.  If involved in acceleration, agree a price before you start. 

 

The architect usually has no contractual responsibility to supply information to the main contractor to suit the requirements of an “early finish” programme.  In so far as some of this information is required for the sub-contractor, then the problems are obvious. 

 

Where the sub-contractor has been signed up on a "target period" from the outset (ie based upon the main contractor's hopes of completing in less than the overall main contract terms allow), then the sub-contractor's obligations and entitlements are governed by this agreed sub-contract period.  Whether or not the main contractor gets an extension of time etc is, probably  irrelevant.

 

 

It's all you've got !

 

 

How else is a sub-contractor to prove his entitlements in respect of delay, disturbance, extension of time and financial reimbursement than by reference to a programme of some kind?   Providing the programme can be shown to have been agreed by the parties in writing, and providing that it corresponds with the sub-contract period and dates as set  out in the original agreement, then an arbitrator would, it is submitted,  be unlikely to dismiss that programme as "irrelevant".

 

 

Conclusion

 

 

In essence, my advice to the sub-contractor is :

 

 

·       Try  to get a programme agreed and incorporated in the original agreement.

 

·       If not, try to get one agreed in writing as soon as possible, and to  establish same as "the baseline programme".

 

·       Retain it in a safe place, as it represents how you started out to tackle the job

 

·       Identify and record the issue and receipt of all revised programmes.

 

·       "Keep an eye" on the main contract progress, and its relevance to sub-contract progress.

 

·       At all times, ask yourself "Is this what the estimator priced to do?"

 

 

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

 

 

 

Back to Jack Russell Column Contents

 

 

Back to home page