EXTENSION OF TIME

 

Essential protection against damages and main contractor’s set-off

 

 

 

Liquidated damages

 

 

Most contracts provide for the contractor to pay the employer liquidated damages at a weekly or daily rate if the project over-runs the completion date.   On major projects, they can be substantial. If the contractor suffers liquidated damages as a direct result of the sub-contractor's default, then he will usually be entitled to recover them from the offending sub-contractor by set-of, together with the  costs of his own  site establishment and staff.  So it is vital that the sub-contractor protects himself by securing a formal extension of time to cover any delay to completion.

 

 

Extension  of time

 

 

Sub-contract conditions usually require the sub-contractor to give written notice of each delay, stating cause, effect upon  progress and estimate of any  effect upon  completion.  The notice is commonly required to be served “forthwith”.  If the sub-contractor delays in giving notice, then he risks forfeiting his entitlements.  As and when the sub-contractor considers the original completion date to be unachievable, he should request an extension of his original period. 

 

The matters giving entitlement to extension of time are usually listed in the sub-contract documents, and are often termed "relevant events".  The events most commonly encountered may be split into two groups (ie “reimbursable”  events which come under the control of the client or contractor, and “neutral” events which fall outside the control of the parties, and bring no reimbursement). 

 

The “reimbursable” events usually include : late issue of instructions and information, effect of variations, delays caused by the client/employer or by his direct contractors and/or suppliers.   A further reimbursable source of entitlement arises from default on the part of the contractor and/or his other sub-contractors (ie delayed availability of workfaces, lack of weatherproofing etc).  These latter delays are usually classed as “act, omission or default”.  If a sub-contractor is delayed due to one or more of these events, he may be entitled to reimbursement of his “prolongation” costs (ie weekly costs of site establishment, supervision, engineering and off site overheads).  If the sub-contractor wishes to claim such costs, he must give written notice as soon as the likelihood becomes apparent. Provision of a budget figure at this stage will also help.

 

The most common “neutral” events include: force majeure (ie circumstances totally beyond the control of the parties), exceptionally adverse weather, strikes and civil commotion, delay by statutory authorities .  Since these carry no reimbursement, most sub-contractors prefer, if practicable,  to concentrate on the “reimbursable” events.

 

 

What makes a good delay notice?

 

 

·       As to the format of a good delay notice, the following check list may help:

 

·       State the area and location of the problem

 

·       State the exact circumstances causing the delay or disturbance

(ie identify the precise  "cause" of the problem).

 

·       Identify "Relevant event" in sub-contract conditions and clause if possible

(eg architect’s instructions, late information, delay caused by the employer, lack of access and/or building progress etc).

 

·       Give the expected effect on programme/progress (ie state which sub-contract activities are affected and how).

 

 

·       State what action is required from other parties in order to avoid or reduce the effect of the delay (eg remove scaffolding, pump out water, provide information etc).

 

·       If  overall completion date is likely to be affected, give an estimate of the delay and the revised completion date.

 

·       Give notice of any cost effects, with details if appropriate.

 

·       Update the notice as necessary, if the delay continues.

 

·       Don't forget to record when the delay has ceased, and the final effect.

 

 

If early warning is given, it may be possible to “nip the problem” in the bud. That will be better for everyone.  Indeed, the sub-contractor should always take a proactive approach and be  ready to suggest solutions. However, these solutions should not be provided at his own expense, nor should they be allowed to endanger  his protection.

        

 

Proving the sub-contractor’s entitlements

 

 

All too often, the contractor will react with a challenge for the sub-contractor to prove his entitlement by “cause and effect”.   This can be achieved by preparing a delay schedule with accompanying charts to show the timing of the delay events in relation to the original programme, the duration of the individual delays and the impact upon completion. However, this will not be possible unless the sub-contractor has maintained good site records (ie site diary, labour allocation register, progress reports, requests for information, confirmation of instructions, daywork sheets, photographs  etc).

 

If  the sub-contractor carries out these obligations from day one, and providing he uses his best endeavours on site, then he should be able to obtain an extension of time and, most importantly, protection from damages and set-off.

 

 

 

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

Back to Jack Russell Column Contents

 

 

Back to home page