EXTENSION OF TIME –
SOME QUESTIONS ANSWERED

 

 

 

Is it true that the client cannot deduct liquidated damages unless he can prove he has incurred them?

No.  Providing the weekly rate of damages was a reasonable estimate at the time the contract was entered into, then the Client can deduct them regardless.

 

 

What about the contractor? Must he show that he has incurred damages or costs before he sets them off against the sub-contractor’s account?

Yes, under most standard forms of sub-contract, such as Dom/1. However, be aware that many contractors are inserting a clause which gives them the right to set off estimated future costs. You should always try to get clauses like this deleted at the outset.

 

 

If a contractor issues the sub-contractor with a revised programme putting the end date back, does this give the sub-contractor an automatic extension of time?

No. This is a common mistake.   You should analyse the programme and identify the factors which have caused the slippage, then apply for extension of time stating the reasons (ie the effects upon the progress of the sub-contract works). If you have  a copy of the original project programme, you will be able to identify the delays in erection of roof, walls, ceilings, partitions etc.  This will be strong evidence to help you if the contractor accuses you of causing delay to project completion.

 

 

Is a contractor right  to refuse the sub-contractor an extension of time  on the grounds that the architect has refused to grant an extension to the main contract?

No. Under the standard forms such as Dom/1, the sub-contractor’s entitlements stand to be judged irrespective of the contractor’s position under the main contract.  For instance, the  contractor may have been guilty of “slow” building, which would give him no entitlement under the main contract. However, the sub-contractor may well be entitled to extension under the sub-contract.  Beware of contractors who insert a clause which restricts the sub-contractor’s rights to benefits arising under  the main contract.

 

 

 

What if the main reason for delay is lack of building progress and/or access?

Under most standard forms, the sub-contractor would have entitlements due to the “act, omission or default” of the contractor.  Again, beware contractors who omit any such clause from their sub-contract conditions. 

 

 

Is it enough for a sub-contractor to give “lack of building progress” as the reason for delay?

No. It is essential to give reasons for the alleged delays (eg incomplete roof to restaurant, lack of internal walls to basement etc).  The sub-contractor  should also state the precise effect on the sub-contract progress (eg delayed start to first fix in restaurant etc). If there is likely to be a delay to overall completion, this must be notified immediately  it  becomes apparent.  This is only fair to the client and contractor, who may be able to take actions to assist progress (eg making alternative work faces available etc).

 

 

Do site minutes qualify as a delay notice?

No.  It is a naïve sub-contractor who relies upon the minutes of a site meeting as a substitute for a proper written delay notice.  In any case, the minutes are usually written by the contractor, and often show considerable bias, not to say distortion.

 

 

If a contractor declines to award an extension of time, and the sub-contractor has to work overtime and/or increase his labour force, can he recover the costs at the end of the job as an “enforced acceleration”?

The main JCT forms and associated sub-contracts make no provision for acceleration. Even if they do, it is a matter to be agreed before putting the measures in hand.   The sub-contractor should emphasise his entitlements to extension, pointing to his notices and records as justification, then by all means put forward proposals for “special measures” and the precise method of reimbursement.  These should be accompanied by provisos regarding timely access, information etc.   However, it is essential to secure written agreement before embarking on any major acceleration.

 

 

Can a sub-contractor be entitled to  prolongation costs before  the original sub-contract end date has passed?

Delays can occur during the progress of the sub-contract works which do not necessarily require extension of the end date. Most services sub-contractors allow a period of several weeks at the end of the programme for “commissioning only”. Only a  residual staff would be required for this. If legitimate delays lead to  reduction of  this period, then the sub-contractor  may well have to retain a full staff on site until the completion date. In such a case, there may well be a legitimate right to prolongation costs (ie the difference between the planned “commissioning” staff and the actual job staff).

 

 

BI-MONTHLY SERIES

ARTICLE NO 5 DATED 30/9/01

 

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

 

 

 

Back to Jack Russell Column Contents

 

Back to home page