VARIATIONS

 

 

 

 

 

Wide definition

 

The standard forms of contract usually give a  wide definition to the term "variation".  It may be stated as including alterations or modifications of design or quality or quantity of the works, additions, omissions or substitutions, alterations  of kinds or standards of materials, alterations in the obligations or restrictions relating to access, working space, hours of work or the order of work.  However, once a sub-contract has been awarded, it is not lawful to remove work from that sub-contractor and to give it another firm. To do so, probably opens the door to a claim for damages (ie loss of profit etc).

 

 

Authority

 

The sub-contractor should ascertain at the outset exactly who is authorised and the procedure for instructing and valuing variations on the particular contract.  Beware of acting on the  direct request of consulting engineers and even more peripheral parties (eg client's co-ordinator, depot manager, etc).  Any such instructions should be confirmed in writing via  the main contractor , since the actual contract relationship is with that party. To ignore this precaution is to risk “working for free”.

 

All variations must be authorised in writing. The JCT standard  forms lay down certain rules as to oral instructions. Usually, there is no obligation to immediately comply. The sub-contractor must confirm any such oral instruction in writing within seven days, if dissent is not forthcoming in a further seven days then the instruction takes effect. If the main contractor himself confirms in writing within seven days of the oral instruction, it takes effect immediately.

 

 

Valuation of variations

 

The valuation  rules set down in most standard forms are based on similar principles, which are reasonably to be implied into "bespoke" forms if the latter are silent on the subject.

Firstly, the bill or schedule rates are not a shopping list.  The rates will only apply if the character, conditions and quantities do not significantly change. 

 

If the conditions under which the work is executed, and/or the quantities of work undergo a significant change, then the bill rates will be used as a basis, with a fair adjustment in respect of  the changes.   If the character of the work changes, then fair rates and prices must be used.  This is not the same as "cost plus". Indeed, if the general level of the bill rates is low, then a "fair" valuation may well reflect this.

 

An astute sub-contractor may well be able, quite legitimately, to secure agreement to starred rates for the majority of his variations.  The list of valid reasons for change in character and/or conditions can be substantial (eg winter working, small quantities, return visits, piecemeal buying, restricted access, high level working etc).  It is essential that the sub-contractor take the initiative if he is to secure his just entitlements.

 

The JCT forms also provide for adjustments to the rates of non-varied contract work where these works have been affected by variations.  Again, this offers considerable scope for wide ranging re-valuation.

 

If  the variation is such that it cannot be measured and valued, then a dayworks basis may be used. Arrangements vary from one form of contract to another (eg "all in rates per hour", "RICS/ECA Definitions with tendered percentages, etc).  Most sub-contracts require prior agreement as to work being done on dayworks, and the prompt submission of vouchers for signature

 

 

Adjustment of preliminaries

 

The JCT forms generally provide for adjustment of preliminaries where such elements have been affected by a variation.  Again, it is up to the sub-contractor to take the initiative.  Strictly speaking, this applies where there is a separate bill of preliminaries. However, an astute sub-contractor should be able to find legitimate reasons for adjustments, even where there is no such bill.

 

 

Who values the variations?

 

Contrary to general belief, the client’s qs and/or the consulting engineer are not contractually responsible for valuation of variations under  domestic sub-contracts. Usually, the valuation stands to be agreed between the two key parties – the main contractor and sub-contractor. 

 

 

 

Loss and expense

 

Many of the circumstances which are treated as "claim situations" in fact fall under "variations" and stand to be valued as such.  The sub-contractor should take the initiative in such matters, since the prospects of fair reimbursement and good cash flow are usually greater when dealing with variations than in a "claims scenario".  The result is a significant improvement in cash flow and reduction in end of job disputes.

 

 

Conclusion

 

The whole business of pricing variations is far more than just “picking from a shopping list of rates”. With appropriate awareness and  ingenuity,  the sub-contractor can do a great deal to ensure being  properly paid for variations and also the original contract works affected by variations.

 

 

ARTICLE NO 6

DATED 4/12/01

FOR END OF December  2001  “TIMES”

FILE biet06

 

 

John Russell  

 Contracts and Training Consultant

 Cheshire CW4 7DP

Tel:  07770 986444 

Email: swsubbie@globalnet.co.uk

 

 

 

Back to Jack Russell Column Contents

 

 

Back to home page