GOVERNMENT
REVIEW OF THE CONSTRUCTION ACT
In the March 2004 budget, the Chancellor announced a review into the workings of the Housing, Grants, Construction and Regeneration Act 1996, Part II, better known as the Construction Act. Since then, a review group chaired by Sir Michael Latham has looked into some of the chief areas of concern relating to abuse and evasion of the Act. Their report has now been issued to the DTI, who will be publishing a consultation document later this year.
The review is the work of two separate working groups, the members being
drawn from various fields within the construction industry, one group dealing
with problems relating to payment, the other concentrating on
adjudication. The key points are summarised below.
The group makes five specific recommendations.
In essence, they are as follows;
·
Strengthening of
suspension of works in cases of non payment.
·
Limitation of
cross contract set-off clauses.
·
Provisions for
payment by a third party where the original payer is insolvent.
·
Removal of Section
110(2) of the Act and its requirements to provide a payment due notice and “due
date” for payment.
·
Clarification of
the “adequate mechanism” requirements under Section 110(1) of the Act.
Unfortunately, because of the mixed nature
of the group and the conflicting interests involved, there were numerous issues
on which agreement could not be achieved and no recommendations are made. These
are:
·
Failure to issue
a withholding notice under Section 111 of the Act, and to provide adequate
detail of reasons for withholding.
·
“Pay when paid”
in cases of insolvency.
·
“Pay when
certified” under the main contract.
·
Payment for off
site works.
·
Lengthening of
payment periods.
·
Statutory rights
to seek security of payment.
Adjudication
The Task Group’s key conclusions regarding the Act and the Scheme
(not always in the form of recommendations) are broadly as follows:
·
Clarification of
the law relating to what constitutes a contract “evidenced in writing”.
·
An end to clauses
requiring the referring party to pay both parties’ costs.
·
Strengthening of
existing statutory protection for adjudicators.
·
Amendment to
Section 108(1) of the Act to read “dispute under or arising out of the
contract”, thereby clarifying the power of adjudicators to decide regarding
damages for breach of contract.
·
Strengthening of
existing requirements of the Scheme regarding the independence of the
adjudicator.
·
Prohibiting of
arrangements requiring sums awarded to be paid into a trustee stakeholder account.
·
Clarification of
timescale regarding 7 days for submission of referral notice.
·
Clarification of
adjudicator’s powers to act on more than one dispute under the same contract.
·
Strengthening of
adjudicator’s powers to award interest.
·
Requirement for adjudicator
always to give reasons unless parties agree otherwise.
·
Amendments to
the Scheme clauses 23 and 24 relating to enforcement of decision, to bring into
line with current practice (ie summary judgment).
·
Clarification of
protection of adjudicator in cases of negligence.
·
Express rights
to be included to enable responding party to serve a response to the referral
notice.
·
New provision
for correction of errors in the adjudicator’s decision, within 7 days of issue.
·
Express
requirement for adjudicator to copy any legal or technical advice to the
parties.
As in the case of payment, the Task Group
were unable to reach agreement on
various matters, which are summarised below:
·
Removing the
present exclusion in relation to PFI contracts.
·
Removing the
present exclusion regarding residential occupiers.
·
Clarification
regarding what contracts should be within the scope of the Act (eg wholly in writing, wholly or partly in
writing, or wholly oral contracts).
·
Removing the
present exclusion regarding the process plant industry.
·
Whether or not
the adjudicator should have the express power to award costs.
·
Implementation
of a single adjudication procedure in all contracts.
·
Adjudicator to
be given express powers to decide on his own adjudication.
·
Rights of parties
to be represented at a hearing by more than one person.
·
Amendment or
removal of paragraph 20(a) of the Scheme , which currently restricts the
adjudicator from opening up decisions or certificates which are described in
the contract as “final and conclusive”.
·
Whether or not
an adjudicator should be called as witness in enforcement procedures.
There are some much needed reforms in the
reports.. However, it looks as if we shall just have to go on living with
problems such as “pay when certified”,
failure to issue a withholding certificate, lengthened payment periods, use of bespoke adjudication procedures,
uncertainty as to what constitutes a contract evidenced in writing, and
inclusion of “final and conclusive” clauses.
John Russell
November 2004
(Based on an
article published in the November issue of “Electrical Times”).
John Russell
Contracts and
Training Consultant
Cheshire CW4 7DP
Tel: 07770 986444
Email: swsubbie@globalnet.co.uk
For more
information on the Construction Act and other contractual matters, refer to my
website at : Home
Back to Jack Russell column.