John Russell  

Construction Contracts & Training Consultant  (Established 1984)

Cheshire CW4 7DP

Tel : 07770 986444   Email : swsubbie@globalnet.co.uk

Website: www.jrconsultant.co.uk

 

 

 

BEWARE THOSE “DESIGN” RESPONSIBILITIES

 

The last few years have seen an increasing tendency for the client’s “design team” to off-load responsibility down the contractual chain. Perhaps this has been influenced by the increasing cost of professional indemnity insurance. Some or all of this responsibility usually falls upon the specialist sub-contractor. With the added responsibility of “design” comes a whole range of contractual and commercial risks. However, these design risks can be minimised by cultivating commercial awareness from the very outset.  Some of the key problem areas are summarised below.

 

Clarity of tender offer

 

Many problems arise from lack of clarity within the original enquiry and tender documents.  It is essential that the sub-contractor’s tender is quite clear as to exactly what the client is going to get for his money.   Is it “full design” or “design development” ?  If “design development” then is the demarcation line clear?  If the sub-contractor is unable to comply fully with the enquiry requirements, then is the tender suitably qualified ?  If  “provisional sums” are included, then are these clear and specific?

 

Duty to warn

 

The specialist sub-contractor has, arguably,  an implied  “duty to warn” at tender stage, regarding elements of “impossibility”.  It is not enough to take the stance of “Well,  that’s what you said you wanted”.   Such “warnings” should be given at the outset.  The text books tell us this is  equally true even when there is no formal design responsibility.

 

Fitness for purpose

 

This is a very onerous obligation, which should be watched for in enquiry documents, and attempts made to exclude from the eventual sub-contract agreement.  Clearly, the risk factor is much higher than the more acceptable criteria of “all due skill and care”.  It has been ruled in the courts that if a contractor undertakes a “design and build” obligation, then “fitness for purpose” applies.  For this reason, the standard forms of contract usually  express the design onus as “all due skill and care”.  However, the position is not always clear, and even less so under non-standard (bespoke) forms.  Few, if any, insurance firms will knowingly accept a “fitness for purpose” risk, and so the careless sub-contractor could well find himself carrying an uninsurable obligation.

 

Client’s warranties

 

Beware the typical “design warranty” which places the sub-contractor at risk, usually for twelve years, to actions from the end client and a whole succession of funders, purchasers and future tenants. Even when  there is no formal design responsibility or warranty, the sub-contractor could well be sued in tort by a party to whom he owes a “duty of care” under law.

 

Approval periods

 

If not stated in the enquiry documents, then does the sub-contractor’s tender specify a “turn round” period for approval of drawings and other submissions ?  At the very least, this needs to be firmed up as soon as possible after receipt of order.

 

Drawing register

 

A drawing register should be set and maintained up from the outset, recording the issue and receipt of all drawings, from whatever source, and detailing reference numbers, titles, dates of issue, status and approval.

 

Preferential engineering

 

Many difficulties and disputes arise from “preferential engineering”. This term may be used to describe the process where, by a subtle process of queries, suggestions and  conditional approvals, the client intrudes into the sub-contractor’s design and selection process, sometimes intentionally but  often without realising it.  “Preferential engineering” can  cause serious  delay and can introduce what are in actual fact “variations” without their being recognised as such.  The sub-contractor must be watchful of this, and ready to nip it, politely but firmly, in the bud.

 

Confirmation of all communications, approvals, instructions etc

 

It is absolutely essential that all communications, approvals, instructions etc be confirmed in writing at the time.   Unconfirmed communications give rise to subsequent differences of recollection as to what was said, or even to total amnesia.  It is almost always the sub- contractor who suffers in these cases.

 

Technical queries

 

All queries and requests for information should be communicated, and/or confirmed, in writing.  A register should be kept, showing date of issue, reference, content, and dates of response and eventual resolution.  It is vital to use a coded reference system which makes it possible to trace the individual links through from initiation to final resolution.

 

“Little  tin gods”

 

“Little tin gods” is a term which aptly describes personnel in the client’s team, and/or other parties on the periphery, on whose “say so” important decisions are taken and/or variations introduced, but who have no proper contractual authority. Typical examples would be : client’s co-ordinators, consulting engineers, works managers, facilities managers etc.  If in doubt, the sub-contractor should ask for written clarification at the outset, as to whether or not a particular party has the requisite authority.  Later on is too late !

 

Conclusion

 

In essence, it is true to say that any ambiguity or discrepancy, however unfairly,  nearly always gets sorted out  at the sub-contractor’s expense.  So the street-wise sub-contractor must  eliminate those “grey  areas”  of design responsibility from the start !

 

 

 

John Russell

 

Based on Jack Russell’s  “Contract Law” column in “Electrical Times”  published 1 October 06.

 

www.jrconsultant.co.uk

 

Back to home page.

 

Back to Jack Russell contents page.