John Russell  FCIOB

Construction Contracts & Training Consultant  (Established 1984)

19 Chester Road, Holmes Chapel, Cheshire CW4 7DP

Tel : 07770 986444   Email : swsubbie@globalnet.co.uk

Website: www.jrconsultant.co.uk

 

 

 

 

EXTENSIONS OF TIME – ANSWERS TO COMMON QUESTIONS

 

Why is a delay notice important?

 

Delay notices are vital to protect the subcontractor’s entitlement to extension of time and act as a shield against financial damages from the main contractor for over run of the original completion date.  An extension of time may also, dependent upon the reasons, entitle the subcontractor to reimbursement of prolongation costs (ie site staff and establishment costs, often referred as “prelims”).

 

When should I submit a delay notice and what should it contain?

 

The notice should be submitted as soon as the likelihood of the delay becomes apparent.  A good delay notice should include date, location and precise cause of delay, action required from  the main contractor, effect on subcontractor's  programme and, if the completion date is likely to be affected, an estimate of likely delay to completion.  Although it may not always be essential, if the completion date is likely to be affected then it is prudent to request an extension of time.

 

Do minutes of meetings qualify as delay notices?

 

Very unlikely.  By all means record your progress and delays in the site minutes. They are very good evidence. However, you still need to submit a written delay notice.

 

What events entitle me to an extension of time and loss and expense?

 

The general rule tends to be as follows : if the delay is due to the client or main contractor (eg variations, late information, end client’s delays, lack of building access etc), then there is entitlement to both time and money, if the delay is due to  a “neutral” event such as weather , strikes or force majeure, then there is time but no money.

 

Do I still need an extension of time when the delay is obviously due to the main contractor’s slow building progress in constructing the project?

 

Yes. The main contractor does  not have to prove the subcontractor’s guilt. If a subcontractor over runs his completion date without an extension of  time, then the main contractor is  probably entitled to deduct damages.

 

The main contractor tells me that he cannot give me an extension of time because he has not been awarded an extension under the main contract. Is he correct?

 

Under a standard form of subcontract like Dom/1, this would not usually be correct. Most standard forms provide for extension due to  “act, omission or default” of the main contractor and/or his other subcontractors (ie lack of building progress and availability of workfaces). Bespoke subcontracts are often worded in a more restricted way.  Even here, a bespoke form of subcontract which makes no provision for extension due to delays caused by the main contractor’s default may still leave a  loophole by way of “time at large” (see below).

 

What is meant by “time at large” and what are the implications?

 

If a subcontract agreement makes no provision for the main contractor to extend the subcontractor’s original period in respect of the former’s “acts of prevention” (eg lack of access, weatherproof conditions or availability of work faces etc) then delays to completion which are caused by such an act may  set time at large. Therefore, bespoke forms which attempt to restrict the subcontractor’s extension to the main contractor’s entitlements under the main contract may in fact let the subcontractor “off the hook”.

 

The effect of time being at large is to deprive the main contractor of an enforceable completion date and leave the subcontractor with an obligation to
complete “in a reasonable time”.  As a result, the main contractor may well lose his automatic right to deduct liquidated damages and  have to pursue his claim as damages at large.

 

The main contractor has issued me with a revised programme showing project completion now delayed by several months. Does this mean I have an extension of time?

 

No, it certainly does not. You need to analyse the revised programme and compare it with the original version.  Look for slippage in construction of the building envelope and the implications upon the subcontract progress. Then request an extension, based on the results of your analysis (eg  delays in access to specific areas, weatherproofing of building, interfacing works by other trades etc).

 

The main contractor told me not to record delays caused by his slow building progress, but to concentrate on variations and late information. He said by doing this we can both get an extension of time and costs attributable to the end client. Should I do as he says?

 

In a word – No.  Many subcontractors have fallen for this old chestnut. At the end of the job, they finish up with no extension of time and no evidence to substantiate the true delays which emanated from the main contractor’s slow building progress.

 

Conclusion

 

It is impossible to overstate the benefit of an extension of time. It protects against damages and gives possible entitlement to reimbursement of the subcontractor’s prolongation costs.  The streetwise subcontractor will make sure that he submits his notices and keeps good records in order to protect his rights.

 

 

Taken from Jack Russell’s “Contract Law” column in “Electrical Times”

published 1 December  06.

 

Back to Jack Russell page.

 

Home.

 

www.jrconsultant.co.uk