THE PFE CHANGE MANAGEMENT SUPPLEMENT

FOR USE WITH THE DELAY AND DISRUPTION PROTOCOL

WHAT THE SUB-CONTRACTOR NEEDS TO KNOW!

 

In previous articles, we have commented on the  “Delay and Disruption Protocol”, published by the Society of Construction Law.  A  supplement is now available to incorporate the key features of the protocol into the JCT forms of contract. It is the PFE Change Management Supplement, jointly produced by the specialist firms of Pickavance Consulting and Fenwick Elliott.  No doubt this will begin to filter down into new enquiries very soon.  To proceed in ignorance is to court disaster! Here are some key headlines.

 

Essential elements of the supplement

The essential elements reflect the protocol itself, and include:

·             Early agreement of a detailed baseline programme with method statements.

·             Regular monitoring with progress reports.

·             Provisions for instruction to accelerate .programme.

·             Prompt identification and recording of time and money events as they become apparent

·             Interim adjustment of time and money as the works proceed

 

Similarity to the NEC contract

The philosophy  and mechanisms appear similar to the NEC contract, with its emphasis on rigid time limits for various actions by the parties. This also applies to the benefits and disadvantages. There are plenty of  both.

 

Risk manager

A new figure is the risk manager, who plays a central role in advising the employer or architect on every aspect of time management. The architect may undertake both roles, if so designated. Ascertainment of loss and expense remains with the architect and/or quantity surveyor.

 

Updated master programme

A master programme is to be established at the outset. All programmes and updates must be prepared in critical path format and transmitted electronically, using approved software. Programmes must be updated at pre-stated intervals and every time an employer’s time risk event occurs. The contractor is liable to damages if he defaults in these duties.

 

Final update

Within 14 days of  practical completion, the contractor must publish his final update of the master programme, recording actual sequences and durations of every activity, including  effects of employer’s time risk events.  Within a further 28 days, he must calculate full details of each employer’s cost risk event and delays to progress, and submit the resultant programme. The risk manager then has  28 days to advise the architect, so that any  loss and expense may be ascertained.  If the contractor fails to comply, the architect has powers to employ others and deduct the costs from the contractor.

 

Management information

The precise format, extent and timing  of the progress reports and site records will be set down in the contract agreement.  The information will include  labour, plant, subcontractor work on site, delivery of materials, instructions issued, weather conditions and any delays occurring. All this information is to be submitted by the contractor at pre-stated periods. Again,  there are financial penalties for non compliance.

 

Acceleration

Most JCT  standard forms make no provision for acceleration. The supplement enables acceleration to be instructed, albeit after due consultation. If the contractor is in culpable delay, then there is no reimbursement of costs. In the case of excusable delay, the instruction counts as a payable  variation for which the contractor must keep contemporary records of costs. If the contractor fails to comply with an instruction to accelerate, he becomes liable for damages.

 

Benefits and disadvantages

The obvious benefits include improved management of change, improved cash flow and minimising of “end of job” disputes.  Disadvantages include compliance with the strict requirements and time limits, and the inevitable need for increased technical staff (particularly planners).  Like the NEC contract, there is a possibility that these procedures may lack the flexibility to cope with a proliferation of delays and variations.  The demand for an updating of programme for each and every employer’s time risk event could prove unachievable. In such cases, the contractor could well lose his legitimate entitlements and incur financial damages from the employer in the process.

 

The sub-contractor

The supplement advises that any necessary linkage should be built into subcontracts. Indeed, if the contractor is to comply with the strict regime of programmes, notices and reports  it will be  essential.   Subcontractors must ensure that they comply from the outset.  Any default will result in loss of entitlements and incurrence of damages.  Additional technical staff will be necessary, notably planners.  The acceleration arrangements require particular consideration. It is possible that the contractor may be in culpable delay and be instructed to accelerate at his own cost. However, the subcontractor may  well have legitimate entitlements to compensation for the same period of delay. Subcontractors should carefully check the wording of any clauses which purport to pass the supplement’s provisions down the line.

 

To find out more about the Delay and Disruption Protocol, please visit my web site at : www.jrconsultant.co.uk

 

John Russell

 

(Based on an article published in the “Contract Law” column of “Electrical Times” – July 2004)

 

Back to Home page

 

Back to Jack Russell column contents

 

John Russell  

 Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk

Contractual  services  * Claims * Training * In house seminars