THE NEW “DELAY AND DISRUPTION PROTOCOL”
A COMMENTARY – Part 2
(Based on an
article published in the “Electrical Times”)
In May, we looked at the “Delay and Disruption Protocol”, released by
the Society of Construction Law, concentrating on programmes, float and
extension of time. In this article, we
continue our examination. The writer’s
comments are given in parentheses.
Concurrent delay
The protocol emphasises that, where
contractor’s own delay runs concurrently with delays caused by the client, this
is not a valid reason for refusing an extension of time. (This is a welcome
clarification, and discourages the common attitude among clients and main
contractors of “The information may well have been late,
but you were not ready”).
Mitigation
Although the contractor has a duty under
common law to mitigate the effect of client’s defaults, this should not involve
the contractor expending additional
resources or working longer hours, unless the conditions of contract expressly
state otherwise. (This confirms my
own advice that no contractor should expend significant costs on “special
measures” to reduce delays by others, unless he has first negotiated an
agreement for reimbursement).
Variations
The protocol recommends pre-agreement of
the price and effect of individual
variations. This includes direct cost,
extension of time and any loss and expense. (This approach is increasingly
found in modern contracts. Unfortunately, the time scales are usually
inadequate, and often made a “condition precedent” to reimbursement. This
places great onus and risk on the contractor). Encouragement is also given to the wider inclusion in contracts of a provision for effect of
variations on non-varied works to be taken into account. (This is already found
in Dom/1, and sub-contractors should take the imitative in securing this
benefit).
Prolongation
The protocol makes clear that, unless
the contract specifically provides otherwise, financial compensation for
prolongation must be on the basis of the loss and/or expense actually incurred
by the contractor. The only exception
may be that caused by variations (see above).
The contractor’s tender
allowances are not to be used, and their adequacy or otherwise is
irrelevant. (This is welcome endorsement of views expressed in leading text books, and
may help claimants in overcoming the misconceived attitudes shown by many
clients and main contractors in responding to prolongation claims. The claimant
is entitled, under common law, to be put back into the position in which he
would have been had the event or breach not occurred. Clearly, this can only be
achieved by reference to actual costs properly incurred and evidenced).
Concurrency in prolongation
Where delays due to the client and the
contractor run side by side, then the protocol advises that costs should only
be payable if the claimant is able to separate the costs caused by the
former. If the costs would have
occurred in any case, then they do not become reimbursable just because a
client’s delay event intervenes. (This
makes good sense, and claimants should analyse the delays in detail, in order
to ensure they can comply).
Time scale of prolongation costs
The protocol emphasises that costs of
prolongation should be valued at the times
when actual compensable delay occurred, not at the tail end over-run. (Many
clients insist that the costs should be those incurred during the eventual
over-run period, when the contractor’s resources have often been reduced in
line with the remaining works. This approach has been very unfair to the
contractor. The protocol’s guidance is therefore very welcome).
Global claims
The protocol frowns on global claims,
and insists that a contractor who has kept good records should be able to show
linkage between the various events and the resultant loss and expense. The
occasional exception may be where the combination of the events make it
impossible to comply. In that case, the
contractor should identify and quantify
those events where cause and effect is possible, and deal with the remainder on
a composite basis. ( This
advice is of little help to the sub-contractor in a typical disruption
scenario. Disturbance of progress does
not usually come from a small number of
major events, but from a multitude of minor preventions. This is often played
out in the absence of any overall
programme from the main contractor, so that progress degenerates into an
ad hoc search for work faces on a daily basis. The result is overall impact on
hourly productivity of labour. Those
clients and main contractors who insist that disruption must be proved by
daywork sheets, and evidence of standing time are, no doubt deliberately,
missing the point).
Conclusion
In the next article, we will deal with
head office overheads and disruption. Meanwhile, the advice must be to submit
prompt notices and keep first class records.
Back to home page – John Russell
John Russell
Construction Contracts & Training
Consultants (Established 1984)
Cheshire CW4 7DP Tel : 07770 986444
Email :
swsubbie@globalnet.co.uk Website:
www.jrconsultant.co.uk