MORE ON THE DELAY AND DISRUPTION PROTOCOL

 

 

In January, we looked at the basics of the  “Delay and Disruption Protocol”, released by the Society of Construction Law.  In this article, we examine some  of the recommendations in more detail.  The writer’s comments are given in parentheses.

 

 

Programme

 

The protocol recommends initial agreement of a master programme, updated on a regular basis and as delay events occur.  For most projects, this should be  a critical path network, with the parties using the same software.  This enables  monitoring,  updating and agreement  on an electronic basis.   The programme should show information requirements and other critical dependencies, and be linked to a comprehensive  method statement. The aim is a programme which always  reflects progress and the current intentions of the project team, and shows how the completion date is to be met.  This provides a management tool for  analysing delays and agreeing any extensions of time as the works proceed. (It is very common for programmes to be superseded by events, with the job left in a state of limbo.  This is why so many subcontractors are left in a position of “ad hoc” working,  and claims for disruption costs. The protocol’s  attempt to reverse this trend is in everybody’s interests.  However, this all presumes that every contractor has the necessary planning resources).

 

 

Programme float

 

General  float in the programme is  for the benefit of the project , rather than “owned by the  contractor”.  A contractor wishing to allow for the possibility of his own delays, should clearly  identify such allowances on his original programme, labelled as “Contingency for …..” against specific activities. (Vague dotted lines will not suffice. Clearly, any contractor who wishes to insert float for his own use must take pains to show precisely when and where this applies, and denote his claim to ownership, perhaps in an explanatory footnote).

 

The protocol suggests that delays which intrude into “end of job” float (ie early finish) may entitle the contractor to financial compensation, provided that, at the time of  contract formation, the employer is aware of the contractor’s intention, which must be realistic and achievable. (This appears to contradict current case law, which states that  the employer has no obligation to assist the contractor to achieve an early finish. I suggest that contractors proceed with great caution in this area).

 

 

Records

 

Format and frequency of records should be agreed at the outset.  These would include progress reports and photographs, delay notices, plant and labour records, dayworks sheets, confirmation of instructions, information required, with daily, weekly and monthly reports which summarise the above. (This is an excellent suggestion. The contractor should take the initiative by asking at the outset).

 

 

Extensions of time

 

Without this mechanism, the end client could lose his rights to liquidated damages, if he committed an act of prevention, since he would then lose the benefit of an enforceable completion date and time would become at large. Therefore, all contracts should provide for extension due to  the client’s own acts, omissions or defaults . (Some bespoke forms of contract which, with the aim of “subbie bashing”, omit such a reference, in fact leave the issuing party exposed).  Secondly, an extension of time protects the contractor against such damages.  However, it does not automatically give financial entitlements, nor is an extension always necessary in order to qualify for financial compensation.  

 

Applications for extension should be submitted and dealt with at the time of the delay event.  The award should be based on the contractor’s true entitlement, not on whether an extension is needed for the contractor to avoid liquidated damages. It is therefore wrong for the architect  to wait to see the final effect of delays before making a decision. (In practice, it will be difficult to persuade architects to conform, unless the terms of the contract insist).

 

Sometimes, after a period of end date over-run due to the contractor’s culpable delay, an employer’s delay occurs (eg late information, a variation etc).    In fact,  any extension entitlement for this isolated employer’s delay should be added back on to the previous completion date. (This confirms existing case law. The common belief amongst contractors that this “gets them off the hook” is incorrect. Clearly, a sprinkling of  late variations of minor nature  will not absolve a contractor for several months of culpable delay).

 

 

Conclusion

 

The protocol’s recommendations are ambitious, and will cost money to operate.  Many smaller firms do not have the necessary staff. However, more attention to these matters at the start and during the contract period, will certainly save money in expensive end of job disputes.

 

 

Bi monthly article  for Electrical Times, May 2003.

 

 

Home

 

Back to Jack Russell column

 

John Russell  

 Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk