MORE ON VARIATIONS

 

 

 

 

In this article, we look at some more problems regarding “variations”, and ways in which the sub-contractor can protect his financial position.

 

 

 

Provisional sums - defined or undefined?

 

 

Where a bill has been prepared in accordance with SMM 7, the rules are very clear. Provisional sums should be  classified in the bill of quantities as either "defined" or "undefined". (SMM 7 general rules 10.1 to 10.6 thereof). These rules are also reflected in the  Dom/1 conditions.

 

If the sums are "defined" then the sub-contractor is deemed to have allowed in his programme and pricing of "prelims".  To qualify as "defined" the bill item must give information about (a) the nature and construction of the work (b) how and where the work is fixed to the building and what other work is fixed thereto (c) a quantity or quantities indicating scope and extent (d) any specific limitations and/or requirements.

 

The provisional sum  does not qualify for the title of "defined", even if so described in the bill, unless it complies with these requirements. Even when compliant, the sub-contractor is still entitled to delay costs and extension of time, where  appropriate, if the  instruction is issued late in relation to the sub-contractor's timely request.

 

If the sums are termed as “undefined”, SMM 7 states that the sub-contractor will be deemed not to have made any allowances for programme effects and/or prelims for undefined sums. Therefore, as and when such sums are instructed, the work involved is, in effect, a variation for "additional work" with full entitlements of extension of time  and loss and expense where this is merited by the nature, timing and/or volume of the work involved. 

 

 

 

Variations after completion

 

 

Most contracts make  no specific provision for "post contract variations".   The sub-contractor should take the initiative  by proposing a revised percentage for dayworks and/or agreement by prior quotation of lump sum, where possible. There is usually  no reason why these post completion variations should be based on the original bill rates. It  is  a matter for agreement between the parties.

 

The sub-contractor should be careful not to go ahead with significant variations issued after practical completion, until he has secured agreement  to the method and level of pricing.

 

 

 

Premature occupation

 

 

Similar remarks apply to the common situation when  the end client  is allowed to take possession on the original completion date, even though the project is still incomplete, through no fault of the sub-contractor.  The sub-contractor then finds himself executing the balance of his works (ie snagging, variations and commissioning)  under conditions of restricted access, changed time scales and congested work faces.

 

In these cases, the sub-contractor must take the initiative by asserting his entitlements under "change of character and/or conditions", dayworks   and/or as loss and expense.  Unless he takes the lead, he will find the main contractor continuing to value the works on the original bill basis.

 

 

 

Omitted works - loss of profit

 

 

It is well established under contract law that  taking away of part or all of a contractor's or sub-contractor's contract works and giving to another firm is a breach of contract. This would entitle the injured party  to damages under the law (ie loss of profit).

 

However, the position regarding the straightforward omission of works is less straightforward.  There is no automatic right to loss of profit in such cases.  It may be possible to show that, in so far as the time related  “prelims” and  overheads  were originally “spread” through the bill prices as a percentage, then any substantial omission  will adversely affect the sub-contractor’s recovery of these time related /or overheads elements. The logical way of redress  would be to increase the percentage allowances (ie make a “fair allowance”) in  the remaining non-varied works.

 

 

 

Interim applications, “getting it in the budget”

 

 

The initiative must rest with the sub-contractor to ensure that the main contractor and/or client  are kept fully informed at all times as to the probable end cost of the sub-contract works.  The sub-contractor must endeavour to price and include his variations in the monthly interim applications.  At the very least, “budget figures” should be included. The bringers of  “nasty surprises” at the end of the job are unlikely to receive sympathy from other  parties.

 

 

 

Notices and records

 

 

It is vital that basic systems are maintained on all sites.  These  include the daily site diary, ( recording work done each day, labour records and activities,  key progress, delays and their origins, major events occurring and special difficulties encountered), drawings register,  confirmation of instructions, and dayworks records. 

 

 

 

Conclusion

 

 

There must be  a system  whereby all variations are identified  and confirmed without delay, and detailed valuations  submitted at the time.  If the sub-contractor follows this approach, there will be great benefits in terms of good cash flow and reduction of disputes.

 

 

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk