OUT OF SYNC!
Sensible subbies will keep weekly records of
their own progress and any delays.
However, these records seldom give
real indication as to the overall picture on the site. A reference to delays awaiting plasterer or
ceiling fixer tells us little about the
overall state of building progress.
Building progress may already be behind when the Subbie is instructed to commence on
site and then slip further. The gallant
Subbie is bullied into pressing on, finding work faces where he can. What is really happening is that he is being
forced to work "out of sync" with the actual rate of
construction. For example, the lack of
plastering could be due to delays in the roof, or internal walls.
As a result, the electrical installations are carried out in radically different
conditions to those contemplated at
tender stage, or by reference to the agreed programme. It is common to see Electricians wading
through lagoons of water and climbing
over heaps of rubble as they carry out second
fix, and even final fix. No wonder
it's hard to make money.
I recommend that the streetwise Subbie tries to get hold of a main contract
programme at the outset, and then monitors the Builder's progress. Whether
these records are released to the Builder will depend on the
circumstances. Admittedly, this is not the way to become "Subbie of the
year". Nevertheless, a record of the overall building delays can be your
best defence against any attempt by the Builder to blame you for delayed completion
of the project.
It is open to the Subbie to apply for financial
adjustment, either by enhancement of
rates to reflect the "changed conditions" of execution, or by
reimbursement of loss and expense. The
problem here is that the buck will normally stop with the Builder, since the
PQS will not be interested in circumstances which derive from default on the
part of the Builder. However, the
Subbie's contractual relationship is with the Builder, and if the worst comes
to the worst, then these matters will have to be pursued in that
direction.
The streetwise subbie will, at the very least,
leaves his options open by keeping good
records and reflecting the overall state of the project as the works proceed. If he decides to let it go, it will be as a policy decision, not
because of ignorance.
John Russell FCIOB
Contracts and
Training Consultant
Email: swsubbie@globalnet.co.uk
Web site: www.jrconsultant.co.uk