THE NEW “DELAY AND DISRUPTION PROTOCOL”

A COMMENTARY – Part 3

 

 

In this article, we continue our examination of the “Delay and Disruption Protocol”, released by the Society of Construction Law, concentrating on head office overheads and  acceleration.  The writer’s comments are given in parentheses.

 

Head office overheads

 

The protocol distinguishes between “dedicated overheads” (ie attributed to a specific compensable event and duly recorded) and “unabsorbed overheads” (eg rent, rates, some salaries of non-specific staff etc).  To successfully recover the latter, a claimant must be able to show: (a) it has actually suffered reduction in overheads recovery during the prolongation period, (b) it has been prevented from recovering overheads elsewhere because resources were tied up by the prolongation.

 

If it is not possible to demonstrate the precise under-recovery by means of specific records, then a formula may be used, albeit with care.  The Hudson formula is not recommended,  because of its dependence on tender inclusion and adequacy. Preference is given to the Emden or Eichleay formulae. The Emden formula is : OHP/100 x contract sum/contract period x period of delay.  The OHP percentage is derived from the claimant’s company accounts.  The Eichleay formula is more complex. To assist, the SCL have a spreadsheet available on www.eotprotocol.com.  (All directors and staff should fill in a weekly timesheet, as a matter of routine, so their time can be costed direct to relevant projects.  It is then easy to calculate and prove resultant  expense arising from prolongation on any specific project. As to the remaining “unabsorbed”  overheads, it may be possible to persuade the respondent to consider a simple “add on” percentage, supported by an auditor’s letter.  These practical steps will greatly reduce need for reliance upon a formula approach.  A cautionary note should be added regarding additional recovery of overheads due to growth in the final account value.  Any formula approach should include an adjustment to reflect this factor. In some cases it may be that the additional recovery of overheads from variations equals or exceeds the loss due to prolongation. In such a case, a claim is hard to pursue.  However, if the majority of the additional recovery occurred during the original contract period, and/or if the compensable events were unrelated to variations, then the claimant may still be able to argue a  case ).

 

Loss of profit

 

The protocol advises that loss of profit on other projects is not generally recoverable under the standard forms.  If such a claim is allowed, the percentage may be derived from the claimant’s audited accounts for the previous three years, with adjustment to reflect  absence of risk.  Alternatively, the parties may agree to use the claimant’s tendered allowance as a basis.  (I do not see why the protocol frowns on loss of profit as a head of claim, provided the claimant can demonstrate that it was capable of earning that profit within its business at the period in question.  Since “direct loss and expense” is equivalent to damages at common law, then loss of profit would appear to be within the contemplation of the parties as a probable consequence of prolongation.  However, the addition of profit as an “add on” to loss and expense is another matter, where the protocol’s advice is clearly valid).

 

Acceleration

 

The protocol emphasises that the contractor cannot be compelled to accelerate to reduce a  client’s delay, unless the contract conditions provide accordingly.  Where there are no such provisions, then the measures and financial arrangements should be agreed before the acceleration is commenced. Having formulated an acceleration agreement, the contractor is not entitled to claim loss and expense for the period of delay which has been avoided by the agreement.

 

The protocol warns contractors not to expect compensation for “constructive accelerations” (ie where a contractor retrospectively argues that he had no option but to accelerate, due to the client’s failure to award an extension of time).  Contractors should deal with this situation by referring the extension of time for dispute resolution.

(The better the contractor’s notices and site records, the stronger will be his position in the event of pressure upon him to accelerate. Such pressure should be resisted, until the detailed measures, such as increased labour resources and weekend working, have been assessed and reimbursement agreed in writing. Vague assurances and “gentlemen’s agreements” are totally inadequate. In fact, virtually all accelerations are later seen to be under-costed.  When pricing the acceleration, the contractor should take account of  factors such as premium time, importation costs, incentive payments, loss of productivity due to extended working hours and increased gang sizes, congested working, additional plant and accommodation.   Another cost will arise from the need for additional supervision to control the enlarged labour force and increase in work faces. In fact, too many contractors fail to increase their supervision, with disastrous results).

 

 

Back to Home page

 

Back to Jack Russell page

 

John Russell

Construction Contracts & Training Consultants (Established 1984)

Cheshire CW4 7DP Tel : 07770 986444

Email : swsubbie@globalnet.co.uk    Website: www.jrconsultant.co.uk